Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 3 of 35.
Rajesh Chowdary said:
1 decade ago
Explanations are good plz share any simple methods other than these
Trupti said:
1 decade ago
1-7/15 should be 6/15 please explaine how 8/15......
Parthiban said:
1 decade ago
@Trupti
1-7/15 = (15-7)/15 = 8/15
I hope this will help you !
1-7/15 = (15-7)/15 = 8/15
I hope this will help you !
Trupti said:
1 decade ago
Thanks Parthiban. I understood well.
Latha said:
1 decade ago
Why the rest part is only 1-7/15 ?
Anshuman said:
1 decade ago
Oh! Thanks I understood well.
Vikas said:
1 decade ago
Thanks for your explanation. But it take much time. Can you tell me tricks.
Suba said:
1 decade ago
Why we subtract with one? can you please explain.
Crompton said:
1 decade ago
Because we know that total work = 1 so we subtract with one.
Depl said:
1 decade ago
Oh! Thanks I understood well.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers