Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
355 comments Page 27 of 36.

Santanu said:   1 decade ago
For those who have difficulty with fractions, here is an alternative.

Let the total work be to lay 120 bricks. (I chose 120 as it can be divided easily by both 15 and 20).

Takes 15 days to lay 120 bricks, That means in one day he can lay 8 bricks.

B takes 20 days to lay 120 bricks. That means B can lay only 6 bricks in one day.

Together they can lay 8+6=14 bricks.

Therefore, in 4 days, they will lay 14*4= 56 bricks only.

Remaining bricks to be layed is 120-56=64 bricks.

That means, 64/120=8/15 of the work is remaining.

Meena said:   1 decade ago
Fraction of work done in 4 days = 7/15.
(It means that out of 15 parts, 7 parts has been done. So 8 parts left)

Therefore, the fraction of work left = 8/15.

MUHAMMAD SHAHID ZAFAR said:   1 decade ago
Why you subtract 7/15 from 1?

Sammed said:   1 decade ago
Thank you, everyone those have written explanation here. It really helps.

Raju said:   10 years ago
In how many days A & B together complete the same job?

Joni said:   10 years ago
Elaborate how you do this (1/50+1/20) where did you get 1/50?

Argan Defar said:   10 years ago
For the Question of @Raju,

(A + B)'s completion days = (A * B/(A + B)),

=> 15 * 20/(20 + 15),

=> 300/35 = 8.6 days.

Pratik D. said:   10 years ago
Since our target is to crack for the competitive exam which means we must do problems as fast as we can to save time, in other words in a short cut way.

Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.

Dipu Ahmed said:   10 years ago
Here,
A works 1/15 in 1 day.
B works 1/20 in 1 day.

So, A + B works (1/15 + 1/20) = 7/60 in 1 day.

So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.

If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.

Asshok said:   10 years ago
Why 1 - 7/15? Explain it.


Post your comments here:

Your comments will be displayed after verification.