Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 26 of 35.

Meena said:   9 years ago
Fraction of work done in 4 days = 7/15.
(It means that out of 15 parts, 7 parts has been done. So 8 parts left)

Therefore, the fraction of work left = 8/15.

MUHAMMAD SHAHID ZAFAR said:   9 years ago
Why you subtract 7/15 from 1?

Sammed said:   9 years ago
Thank you, everyone those have written explanation here. It really helps.

Raju said:   9 years ago
In how many days A & B together complete the same job?

Joni said:   9 years ago
Elaborate how you do this (1/50+1/20) where did you get 1/50?

Argan Defar said:   9 years ago
For the Question of @Raju,

(A + B)'s completion days = (A * B/(A + B)),

=> 15 * 20/(20 + 15),

=> 300/35 = 8.6 days.

Pratik D. said:   9 years ago
Since our target is to crack for the competitive exam which means we must do problems as fast as we can to save time, in other words in a short cut way.

Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.

Dipu Ahmed said:   9 years ago
Here,
A works 1/15 in 1 day.
B works 1/20 in 1 day.

So, A + B works (1/15 + 1/20) = 7/60 in 1 day.

So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.

If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.

Asshok said:   9 years ago
Why 1 - 7/15? Explain it.

Kennethy said:   9 years ago
@ Vishwanath.

7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.

Hence it is 7/15.


Post your comments here:

Your comments will be displayed after verification.