Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 26 of 35.
Meena said:
9 years ago
Fraction of work done in 4 days = 7/15.
(It means that out of 15 parts, 7 parts has been done. So 8 parts left)
Therefore, the fraction of work left = 8/15.
(It means that out of 15 parts, 7 parts has been done. So 8 parts left)
Therefore, the fraction of work left = 8/15.
MUHAMMAD SHAHID ZAFAR said:
9 years ago
Why you subtract 7/15 from 1?
Sammed said:
9 years ago
Thank you, everyone those have written explanation here. It really helps.
Raju said:
9 years ago
In how many days A & B together complete the same job?
Joni said:
9 years ago
Elaborate how you do this (1/50+1/20) where did you get 1/50?
Argan Defar said:
9 years ago
For the Question of @Raju,
(A + B)'s completion days = (A * B/(A + B)),
=> 15 * 20/(20 + 15),
=> 300/35 = 8.6 days.
(A + B)'s completion days = (A * B/(A + B)),
=> 15 * 20/(20 + 15),
=> 300/35 = 8.6 days.
Pratik D. said:
9 years ago
Since our target is to crack for the competitive exam which means we must do problems as fast as we can to save time, in other words in a short cut way.
Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.
Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.
Dipu Ahmed said:
9 years ago
Here,
A works 1/15 in 1 day.
B works 1/20 in 1 day.
So, A + B works (1/15 + 1/20) = 7/60 in 1 day.
So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.
If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.
A works 1/15 in 1 day.
B works 1/20 in 1 day.
So, A + B works (1/15 + 1/20) = 7/60 in 1 day.
So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.
If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.
Asshok said:
9 years ago
Why 1 - 7/15? Explain it.
Kennethy said:
9 years ago
@ Vishwanath.
7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.
Hence it is 7/15.
7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.
Hence it is 7/15.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers