Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 24 of 35.
Shashi kant said:
10 years ago
A's days = 15.
B's days = 20.
LCM of both = 60 (total work also).
A's work per day = 60/15 = 4.
B's work per day = 60/20 = 3.
Both can do work in one day = (4+3) = 7.
4 days work of both = 7*4 = 28.
Then remaining work = (60-28) = 32.
So please tell me how can I fractionate it?
B's days = 20.
LCM of both = 60 (total work also).
A's work per day = 60/15 = 4.
B's work per day = 60/20 = 3.
Both can do work in one day = (4+3) = 7.
4 days work of both = 7*4 = 28.
Then remaining work = (60-28) = 32.
So please tell me how can I fractionate it?
Mouni said:
10 years ago
A's days = 15.
B's days = 20.
LCM of both = 60 (total work also).
A's work per day = 60/15 = 4.
B's work per day = 60/20 = 3.
Both can do work in one day = (4+3) = 7.
4 days work of both = 7*4 = 28.
Then remaining work = (60-28) = 32.
So please tell me how can I fractionate it?
B's days = 20.
LCM of both = 60 (total work also).
A's work per day = 60/15 = 4.
B's work per day = 60/20 = 3.
Both can do work in one day = (4+3) = 7.
4 days work of both = 7*4 = 28.
Then remaining work = (60-28) = 32.
So please tell me how can I fractionate it?
Keshav said:
10 years ago
Nice explanation.
ANI KONAR said:
9 years ago
Short trick:
15, 20 LCM 60.
4, 3 efficiency.
4 + 3 = 7 in 1 day.
7 * 4 = 28 in 4 days.
Remaining = 60 - 28 = 32.
In fraction 32/60 = 8/15.
15, 20 LCM 60.
4, 3 efficiency.
4 + 3 = 7 in 1 day.
7 * 4 = 28 in 4 days.
Remaining = 60 - 28 = 32.
In fraction 32/60 = 8/15.
Harkanwal said:
9 years ago
Why 32 by 60? Explain in detail.
Basivireddy said:
9 years ago
Hi guys, this is Basivireddy.
A can be work in 15 days = 1/15.
B Can be work in 30 days = 1/30.
1/15 + 1/30.
7/60 this is one day work.
We want 4 days work that's why it is 4*7/60 = 28/60 = 7/15.
Now one day work means they left one day so.
1-7/15 = 8/15, I hope so you understood, Thank you guys, have a great day.
A can be work in 15 days = 1/15.
B Can be work in 30 days = 1/30.
1/15 + 1/30.
7/60 this is one day work.
We want 4 days work that's why it is 4*7/60 = 28/60 = 7/15.
Now one day work means they left one day so.
1-7/15 = 8/15, I hope so you understood, Thank you guys, have a great day.
Vikas said:
9 years ago
Can you explain how is 7/60 came?
GANESH said:
9 years ago
A do the work in 1 day is = 1/15.
B do the work in 1 day is = 1/20.
So LCM of 15, 20 is = 60.
Now,
A's work is 1/15 * 60 = 4.
B's work is 1/20 * 60 = 3.
Then (4 + 3/60) = 7/60.
7/60 is one day work of A+B.
We want 4 days work of A+B.
Then,
(4 * 7/60) = 28/60.
=> 7/15.
Now one day work is (1 - 7/15) = 15 - 7/15.
=> 8/15 is the answer.
B do the work in 1 day is = 1/20.
So LCM of 15, 20 is = 60.
Now,
A's work is 1/15 * 60 = 4.
B's work is 1/20 * 60 = 3.
Then (4 + 3/60) = 7/60.
7/60 is one day work of A+B.
We want 4 days work of A+B.
Then,
(4 * 7/60) = 28/60.
=> 7/15.
Now one day work is (1 - 7/15) = 15 - 7/15.
=> 8/15 is the answer.
Nanda said:
9 years ago
How you got 7/15?
Anoof said:
9 years ago
60 divides 4 by 15 times that means 4 * 15 = 60.
Post your comments here: