1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 24 of 35.

Shashi kant said:   10 years ago
A's days = 15.

B's days = 20.

LCM of both = 60 (total work also).

A's work per day = 60/15 = 4.

B's work per day = 60/20 = 3.

Both can do work in one day = (4+3) = 7.

4 days work of both = 7*4 = 28.

Then remaining work = (60-28) = 32.

So please tell me how can I fractionate it?

Mouni said:   10 years ago
A's days = 15.

B's days = 20.

LCM of both = 60 (total work also).

A's work per day = 60/15 = 4.

B's work per day = 60/20 = 3.

Both can do work in one day = (4+3) = 7.

4 days work of both = 7*4 = 28.

Then remaining work = (60-28) = 32.

So please tell me how can I fractionate it?

Keshav said:   10 years ago
Nice explanation.

ANI KONAR said:   9 years ago
Short trick:

15, 20 LCM 60.

4, 3 efficiency.

4 + 3 = 7 in 1 day.

7 * 4 = 28 in 4 days.

Remaining = 60 - 28 = 32.

In fraction 32/60 = 8/15.

Harkanwal said:   9 years ago
Why 32 by 60? Explain in detail.

Basivireddy said:   9 years ago
Hi guys, this is Basivireddy.

A can be work in 15 days = 1/15.

B Can be work in 30 days = 1/30.

1/15 + 1/30.

7/60 this is one day work.

We want 4 days work that's why it is 4*7/60 = 28/60 = 7/15.

Now one day work means they left one day so.

1-7/15 = 8/15, I hope so you understood, Thank you guys, have a great day.

Vikas said:   9 years ago
Can you explain how is 7/60 came?

GANESH said:   9 years ago
A do the work in 1 day is = 1/15.
B do the work in 1 day is = 1/20.

So LCM of 15, 20 is = 60.

Now,

A's work is 1/15 * 60 = 4.
B's work is 1/20 * 60 = 3.

Then (4 + 3/60) = 7/60.

7/60 is one day work of A+B.

We want 4 days work of A+B.

Then,

(4 * 7/60) = 28/60.

=> 7/15.

Now one day work is (1 - 7/15) = 15 - 7/15.

=> 8/15 is the answer.

Nanda said:   9 years ago
How you got 7/15?

Anoof said:   9 years ago
60 divides 4 by 15 times that means 4 * 15 = 60.