Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
351 comments Page 19 of 36.

MEGA MATH said:   5 years ago
1/15 + 1/20 = 7/60,
7/60*4 = 28/60,
If we simplify 28/60 by 4, then it is 8/15.

Sowmi said:   1 decade ago
Why the value of b had multiplied but in final there is a subtraction is held?

Dinesh kumar said:   3 years ago
A = 1/15
B = 1/20
(A+B) = 1/15+1/20 = 7/15
The remaining work = 1-7/15 = 8/15.
(26)

Deepa said:   10 years ago
@Swetha.

Thanks! Your explanation is very good and it is easy to understand.

Jeevanantham M said:   3 years ago
@Ayansh.

For this;

(A+B) 's work rate = 1/15 + 1/20 = (4/60 + 3/60) = 7/60.
(21)

Mani said:   9 years ago
How to find the solution of this question? Please solve this by easy method.

Vikas said:   1 decade ago
Thanks for your explanation. But it take much time. Can you tell me tricks.

Rajendra said:   1 decade ago
Good explanation but I can't understand how the 1- (7/15) is became 8/15.

Nagasuriya said:   1 decade ago
Dear friends how to solve this calculate 7/60 x4 =7/15 please explain me?

Sammed said:   10 years ago
Thank you, everyone those have written explanation here. It really helps.


Post your comments here:

Your comments will be displayed after verification.