Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 17 of 35.

ANURAG SAXENA said:   1 decade ago
LCM - 15, 20.
LCM = 60 UNIT.

A-- 15 DAY -60/15 = 4 U/D
B -- 20 DAY -60/20 = 3 U/D

A+B = 7 U/D.

4 DAYS = 7x4 = 28 U.

REAMING UNIT = 60-28 = 32 UNIT.
REAMING WORK = 32/60 = 8/15 DAYS.

Prathyusha said:   1 decade ago
Why we takes total work as 1?

Prashant said:   1 decade ago
@Deepa.

Actually when fraction occur.
Then base must be same while doing it.

1/15 + 1/20 in this situation to calculate it base must be same. We can make it by multiply 1/15 By 4 and 1/20 By 3 so that it will be:

4/60 and 3/60 so.4/60 + 3/60 now we can do calculation result 7/60.

I hope you understand what I mean to say?

Priya said:   1 decade ago
Is there any easy tricks to proceed further?

Krishna gummani said:   1 decade ago
A can do a work in 15 days.
B can do the work in 20 days.

i.e. in one day the work completed by A and B is 1/15 and 1/20 respectively.
In one day the work done by both A and B is, 1/15+1/20 = 7/60.

If, for one day the work done is 7/60, then for four days?
7/60*4 = 28/60.

The total work is 1.
Work done in 4 days is 28*60.
Then, remaining work is to be done is 1-28/60.

i.e. 8/15.

Hence proved.

Kali said:   1 decade ago
1/15 = 4/60.
1/20 = 3/60.

Simply add 4+3 = 7.
And copy the denominator 60.

LCD:
15 = 5x3.
20 = 5x4.

LCD = 5x3x4 = 60.

Vikki ls said:   1 decade ago
Hi sir,

How would you calculate the 7/16*4 for to knowing the 4/15=60 ?

Please tell me sir.

Deepak said:   1 decade ago
Why are using 1-7/15?

Sassy said:   1 decade ago
I'm not getting it at all can someone explain it why 70/60 in the easiest explanation please.

Srikanth said:   1 decade ago
In all these problems total work taken as "1" so we have to remove the resulting answer i.e., 7/15 from total work"1" so remaining work is (1-7/15) i.e., 8/15.


Post your comments here:

Your comments will be displayed after verification.