1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 14 of 35.

Sujit said:   1 decade ago
@Dipen:

Probability is always .....Total chance = 1.

If you say chances of wining a match is 1/2 i.e.(50%) it means chances of losing match is also 1/2 (50%)...how this losing chances 1/2 comes?

It comes from subtracting wining chances from total chance that is : 1-1/2 = 1/2

Similarly in above question

Remaining work = total work (1) - 4 day's work (7/15) = 8/15

Hope you get this...Have a great time :-)

Raj said:   1 decade ago
Can anyone explain answer for the below please?

A and B can together do a piece of work in 30 days. B alone can do it in 40 days. A alone can do it in ? days.

For me its coming 120 days. But in TNPSC ans is 140 days. please explain.

Arun D C said:   1 decade ago
@Raj, Here is the solution for yours.

Given:

A + B = 1/30 (A and B together can do the work in a single day).

B = 1/40 (B alone can do the work in a single day).

Solution:

A = (A+B) - B.
= 1/30 - 1/40.
= (4-3) / 120.
= 1 / 120.

A = 1 / 120 (A alone can do the work in a single day).

Therefore 'A' alone can complete the work in 120 days.

Carlo said:   1 decade ago
4(1/15 + 1/20) + X = 1.

X = 8/15.

Kumar said:   1 decade ago
Why are we subtracting 7/15 from 1 ?

Why not any other number?

Tinu said:   1 decade ago
Because a work is calculated as 1.

If any value coming under fraction it comes between 0 to 1 so only.

Like 15/15 = 1.

Likewise Here we have 7/15 only, we need to know the remaining.

15/15-7/15 = 15-7/15 = 8/15.

Geek said:   1 decade ago
1-((1/20+1/15)*4)==>1-7/15==>8/15.

This is easy method, I think. If any other easy method please give me.

Mukesh Mishra said:   1 decade ago
A's 1 day work=1/15; B's 1 day work = 1/20.

OK. Then we calculate how much A + B can do in 1 day.

i.e. 1/15 + 1/20 ( in fraction if denominator is different first we find the l.c.m of denominator). So we calculate the l.c.m of 15 and 20 i.e 60(15 and 20 is divided by 5 we get the answer 3 and 4 so we find l.c.m by multiplying 5*3*4=60). 1/15*60+1/20*60 = 4+3/60 = 7/60.

If A and B do work in 4 days = 7/60*4 = 7/15.

Remaining work = 1-7/15 = 8/15 [ (15*1-7)/15 = 8/15.

DEEPAK said:   1 decade ago
A = 20, B = 15.

TOTAL WORK FOR ONE DAYS = 7/60.

4 DAYS = 7/15.

Remaining work = 8/15.

Sowmi said:   1 decade ago
Why the value of b had multiplied but in final there is a subtraction is held?


Post your comments here: