Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 14 of 35.
Vikrant said:
9 years ago
Simple that how get 7/60. 15 + 20/15 * 20 = 35 / 300.
So, 7 * 5 = 35 & 60 * 5 = 300. Thats it!
So, 7 * 5 = 35 & 60 * 5 = 300. Thats it!
Koteswararao chimmili said:
9 years ago
A's 1 day's work = 1/15;
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15 + 1/20)
LCM = 60
5 | 15 , 20
__________
3 , 4
= 5*3*4 = 60
(A + B)'s 1 day's work = (4/60 + 3/60) ( 4/60 = 1/15 AND 3/60 =1/20 )
= 7/60
(A + B)'s 4 day's work = 7/60*4
= 28/60
= 7/15 .
Therefore, Remaining work = (1 - 7/15)
= (15-7)/15
= 8/15.
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15 + 1/20)
LCM = 60
5 | 15 , 20
__________
3 , 4
= 5*3*4 = 60
(A + B)'s 1 day's work = (4/60 + 3/60) ( 4/60 = 1/15 AND 3/60 =1/20 )
= 7/60
(A + B)'s 4 day's work = 7/60*4
= 28/60
= 7/15 .
Therefore, Remaining work = (1 - 7/15)
= (15-7)/15
= 8/15.
Israel said:
9 years ago
A can do the work in 15days, hence he does 1/15 of the work in a day.
B can do the work in 20days, hence he does 1/20 of the work in a day.
Working together, they will do (1/15)+(1/20)= 7/60 of the total work.
In 4 days, they would have done 4 * (7/60) = 7/15 of the total work (E.g they have built 7 houses out of the 15 houses they were to build).
Hence, they need to build 8 more houses to complete their work. That is how we get 8/15 as the FRACTION of work remaining.
I hope that was comprehensive enough.
B can do the work in 20days, hence he does 1/20 of the work in a day.
Working together, they will do (1/15)+(1/20)= 7/60 of the total work.
In 4 days, they would have done 4 * (7/60) = 7/15 of the total work (E.g they have built 7 houses out of the 15 houses they were to build).
Hence, they need to build 8 more houses to complete their work. That is how we get 8/15 as the FRACTION of work remaining.
I hope that was comprehensive enough.
Mani said:
9 years ago
How to find the solution of this question? Please solve this by easy method.
Sri said:
9 years ago
Please give the short trick 'with efficiency' then the sum will be solved very quickly.
Kennethy said:
9 years ago
@ Vishwanath.
7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.
Hence it is 7/15.
7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.
Hence it is 7/15.
Asshok said:
9 years ago
Why 1 - 7/15? Explain it.
Dipu Ahmed said:
9 years ago
Here,
A works 1/15 in 1 day.
B works 1/20 in 1 day.
So, A + B works (1/15 + 1/20) = 7/60 in 1 day.
So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.
If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.
A works 1/15 in 1 day.
B works 1/20 in 1 day.
So, A + B works (1/15 + 1/20) = 7/60 in 1 day.
So, if A + B works together 7/60 in 1 day.
Then A + B works together (7/60 * 4) = 8/15 in 4 day.
If we assume that 1 is the full work and A+B works together 8/15 in 4 days .
The remaining works we get by {full work - (A + B)'s 4 days completed works}.
So , (1 - 8/15) = 7/15.
So, the answer is 7/15.
Pratik D. said:
9 years ago
Since our target is to crack for the competitive exam which means we must do problems as fast as we can to save time, in other words in a short cut way.
Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.
Now, for this question, lets suppose they are making chairs (the work).
A takes 15 days. B takes 20 days. Then LCM of 15, 20 is 60.
Capacity of A = 4 chair/day and capacity of B = 3 chairs/day.
So A + B capacity in one day = 4 + 3 = 7 chairs/day,
The question says for 4 days they worked together. ie (7 * 4 = 28).
Remaining = 60 - 28 = 32.
Fraction of work remaining = 32/60 = 8/15.
Argan Defar said:
9 years ago
For the Question of @Raju,
(A + B)'s completion days = (A * B/(A + B)),
=> 15 * 20/(20 + 15),
=> 300/35 = 8.6 days.
(A + B)'s completion days = (A * B/(A + B)),
=> 15 * 20/(20 + 15),
=> 300/35 = 8.6 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers