Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 29)
29.
A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
53 comments Page 5 of 6.

Priya said:   9 years ago
I didn't get why 7/4 is used?

Please explain.

Pawan narkhede said:   1 decade ago
How to come A is 7/4 times efficient than B?

Swapna said:   8 years ago
7+4=11......28 ,7....? 11/7*28 = 44 ans.

Bharathi said:   8 years ago
It's easy to understand. Thanks @Kuntal.

Girish said:   1 decade ago
Why we should multiply by 7 at the end ?

Varun said:   1 decade ago
Ratio type problem solve by 'x' value.

Raj said:   1 decade ago
How we get A =7/4? Please help me.

Hellani said:   8 years ago
Can you please explain me? Please.
(1)

Pankaj said:   1 decade ago
How Total Working Days=7*4=28 ?

Prabhu said:   8 years ago
Nice explanation @Jimmy John.


Post your comments here:

Your comments will be displayed after verification.