29.
A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
53 comments Page 4 of 6.

Priya said:   9 years ago
I didn't get why 7/4 is used?

Please explain.

Siri said:   9 years ago
How you are getting 7/4? Anybody explain it please.

Shadab Akhtar said:   9 years ago
@priya & siri, 7/4 is given in question itself, when you will solve the fraction part you will get it.

A+B = 1/7 (given). 1.

A = 7/4*B (given). 2.

B = 4A/7 (from 2).

Put the value of B in eq 1.

A+4A/7 = 1/7.

A = 1/11.

So A will do the work in 11 days.
(2)

Juhi said:   9 years ago
If 4/7 of a piece of work is completed in 7/4 days, in how many days can rest of the work be completed?

Kriti said:   9 years ago
Guys I am not getting the concept of equation 1 and 2 please any one explain me in detail, please.

ASHRAF said:   9 years ago
Can also do by LCM method A is 1.75 times of effort b ie... 1 3/4 is equal to 1.75...if B is work spree is B then A will be 1.75B is same. So work done by A+B in 7-days is equal to A's work in x days.

So 2.75B * 7 = 1.75B * X,
Solve you get X = 11.
(1)

Anil kumar reddy said:   9 years ago
a + b = 7 days.
a = 7/4 * b.
Therefore a + 4/7a - 7 days {since men is inversely proportional to days}.

11a/7 - 7 days for getting a divide with 11/7 and another side multiply with 11/7 then we get 11 days to get complete by alone.

Vaibhav jain said:   9 years ago
Let,

A = x.
B = 7/4x.
Total work = 7x (i.e. Lcm of A &B).
A's one day work = 7.
B's one day work = 4.
(A + B)'s one day work = 11.
As we know that total work we have 7x.
Using formula of work --->(total work/(A+B) one day work) = (A+B) total work.
7x/11 = 7--->x=7*11/7--> x = 11 i.e total days of x.

Sm Jahid said:   9 years ago
Let,
A do the job = X day.
and B do the job = 7X/4.

By the question,
1/X+4/7X = 1/7,
=> 7+4/7X = 1/7,
=> 7X = 77,
=> X = 11.

So A do the job in 11 days.
(1)

Vams'trick said:   8 years ago
B complete work in days = X.
A take days = 4X/7,
A+B work in 1 day = 7/4X + 1/X,
But from problem it is 1/7,
7/4X + 1/X = 1/7,
X =77/4 = B,
A = 4X/7= 4/7 * 77/4 = 11.
(1)