A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ;
6

(A + B)'s 1 day's work = 1 ;
8

(B + C)'s 1 day's work = 1 .
12

Therefore (A + C)'s 1 day's work
= ( 2 x 1 ) - ( 1 + 1 )
6 8 12
= ( 1 - 5 (
3 24
= 3
24
= 1 .
8

So, A and C together will do the work in 8 days.

Discussion:
53 comments Page 4 of 6.

Mukesh said:   1 decade ago
Any tell me how to solve this sum in L.C.M?

Vick said:   1 decade ago
A's = (A+B+C) - (B+C) = 1/6-1/8 = 1/24.
B's = (A+b+C) - (A+B) 1/6-1/12 = 1/12.

A+C's (1/24) + (1/12) = 1/8.

Therefore they can complete in 8 days.

ROHINI said:   1 decade ago
Given a+b=1/8, b+c =1/12, a+b+c =1/6, a+c =?
a+b+c = 1/6.

Sub a+b & b+c in above equ.
1/8 + c = 1/6.
c = 1/24.
a+1/12 = 1/6.
a = 1/12.
a+c = 1/12 +1/24 = 3/24 = 1/8.

Hussain said:   1 decade ago
Hey guys please say me.

How 1/12+1/24 = 1/8.

I did not understand the logic the lcm of these two numbers is 24.

Nisha said:   1 decade ago
Why 2 is multiplied with 1/6.

To find out (A+C)'s work the equation is 2(A+B+C)-((A+B)+(B+C)).
On solving this equation,

A+B+C = 1/6;
A+B = 1/8;
B+C = 1/12;

(A+C)= 2(1/6)-(1/8+1/12),
= 1/8.

Husam said:   1 decade ago
One day's work for (A+B) is 1/8.
One day's work for (B+C) is 1/12.
One day's work for (A+C) is 1/X.

So,

(A+B)+(B+C)+(A+C) = 1/8+1/12+1/x.
2(A+B+C) = 1/8+1/12+1/x.
2*1/6 = 1/8+1/12+1/x.
1/x = 2*1/6-(1/8+1/12).
x = 1/8.

So,

One day's work for (A+C) = 1/8.
A and C finish work in 8 days.

Iqbal sofi said:   1 decade ago
This can be easily solved as:
Given that,

A+B=8 => A+B=1/8;..........(1).
B+C=12 => B+C=1/12;...........(2).
&
A+B+C=6 => A+B+C=1/6;...........(3).
solving eq (3).

A+(B+C) = 1/6.
A+(1/12) = 1/6.
A = 1/6-1/12.
A = 1/12.

Substitute A in eq (1),
A+B = 1/8.
(1/12)+B = 1/8.
B = 1/8-1/12.
B = 1/24.

now substitute B in eq (2)
B+c=1/12
(1/24)+c=12
c=1/12-1/24
c=1/24

Question is A+c=?
(1/12)+(1/24).
1/8.

Therefore A and C can do the work in 8 days.
(2)

Sk.Gopinath said:   1 decade ago
A+B+C = 1/6;
A+B = 1/8;
B+C = 1/12;

C's 1day work is =>1/6 - 1/8
=>1/24.
A's 1day work is =>1/6 - 1/12
=>1/8.

A+C 's 1day's work =>1/24 + 1/12.
= 1/8 = 8 days.

Monu said:   1 decade ago
Why can't we simply subtract A+B's 1 day work from B+C's 1 day work to get A+C's 1 day work?

Dhanshree said:   1 decade ago
(A+B) work is = 1/8.

(B+C)work is = 1/12.

(A+B+C)work is = 1/6.

Only A's work = 1/6-1/12

= 1/12.

Only C's work=1/6-1/8

= 1/24.

Hence (A+C)'s complete work is = (1/12+1/24)

= 1/8.

(A+C)'s complete work in 8 day.