Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 26)
26.
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ;
6

(A + B)'s 1 day's work = 1 ;
8

(B + C)'s 1 day's work = 1 .
12

Therefore (A + C)'s 1 day's work
= ( 2 x 1 ) - ( 1 + 1 )
6 8 12
= ( 1 - 5 (
3 24
= 3
24
= 1 .
8

So, A and C together will do the work in 8 days.

Discussion:
54 comments Page 2 of 6.

Ivan said:   4 years ago
Thanks for explaining @Parveen Verma.
(1)

Nandhu said:   9 years ago
a+b=8,b+c=12,a+b+c=6.
LCM(8,12,6)=24.
a+b=24/8=3,b+c=24/12=2,a+b+c=24/6=4,
(a+b+c)-(a+b)=1,(a+b+c)-(b+c)=2,
c=1 a=2.
a+c=3,24/3=8.
ans:8.
(1)

Santosh said:   9 years ago
A+B ....8 DAY- 3unit. L.C.M-24 UNIT
B+C......12 DAY - 2 unit.
A+B+C......6 DAY -(24/6)...4 unit .

Then,
A+B+C=4. A+B=3....(3+C=4 =C=1)
C=1.
B+C=2 UNIT .....C=1.
B=1.
A+B=3.
B=1.
A=2 .
A and c's work.
A+c=2+1=3 unit per day,
Total work =24 unit,
A+c=24/3=8 day.

Vishal sinha said:   8 years ago
It can be done in a much simpler way.

(A+B)'s 1-day work = 1/8.
(B+C)'s 1-day work = 1/12.

(A+B)+(B+C)'s 1 day work= 1/8+1/12.
B+(A+B+C)=5/24,
B=5/24-1/6,
B=1/24.

So, A+B+C=1/6,
Putting the value of B.

(A+C)'s 1 day work = 1/6 - 1/24 = 1/8.

Time taken = 8 days.

Deep said:   9 years ago
Thanks @Parveen.

Vikas said:   9 years ago
Thanks for the explanation.

Dimple said:   9 years ago
Thank you for all your explanations.

Gregory wachiye said:   1 decade ago
This is awesome. I have gained a lot with the help of this explanations.

Raghav said:   1 decade ago
Excellent guys! Keep it up.

Chary said:   9 years ago
good explanation, thanks all.


Post your comments here:

Your comments will be displayed after verification.