Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 3 of 23.

Ion Strait said:   2 years ago
The reason that 5/48 becomes 48/5 is that C's one day work = 5/48.
Here it means, the total work in units is 48 and out of that C does 5 units of work in 1 day, so it's 5/48.
But the question asks the time required for C alone to complete the work.
Since, 48 units are the total work, just divide it by the one-day unit of C's work, that is, 5
So, 48/5.
(50)

Abhishek said:   10 years ago
A - 16 days | 3 unit/day

L. C. M of (16, 12, 4).

| | = 48.

B - 12 days |4 unit/day|.

| |.

C - ? |x unit/day|.

-------------------------------------------------.

(A+B+C) - 4 days | 12 unit/day |.

So, for C we get (12-3+4) = 5 unit/day.

If C can do 5 unit in 1 day, then 48 unit can be done in 48/5 = 9*3/5 days.

Guys this is the easiest way.

Ammu said:   8 years ago
@Shruti.

A's one day work = 1/16.
B's one day work = 1/12.
with the help of C , they finished in 4 days.
So, A+B+C=4 days,
Therefore, (A+B+C)'s one day work = 1/4.
If C alone is = X.
then 1/16+1/12+X = 1/4,
X= 1/4-(1/16+1/12) {Lcm of 16, 12 is 48 and by the cross multiplication will get 7/48}
= 1/4-7/48,
= 12-7/48,
= 5/48,
C's one day work = 5/48.

Shakir said:   1 decade ago
We know a formula that,

If A do a work in X days, B do a work in Y days and C do a work in Z days.
Then all of three can do the same work in = XYZ/(XY+YZ+ZX).

Then,
According to question,

A do a work in 16 days,B do the same work in 12 days and let C do the same work in Days
Then we can write as,

(16*12*x)/(16*12+12x+16x) = 4.

And solve it.

Talib said:   4 years ago
A = 16.
B = 12.
A + B + C = 4.

Total work by a, b, c ie LCM of 16, 12, 4 = 48.

Then A work in 1 day = 48/16 = 3unit.
and B work in 1 day = 48/12 = 4 unit.

And A +B+C work in 1 days = 48/4= 12 unit.
Therefore put value of a and b ie 3 + 4 + c = 12.
ie c work in 1 day = 5 unit.
Therefore total work done by C is 48/5 ans simple and fast method.
(3)

Aparna said:   1 decade ago
@gurjit
as per formula,
If A's 1 day's work = 1/n , then A can finish the work in n days.
here also same
c's one days work=5/48
hence he can complete whole work in 48/5 days,tats asked to us

and remember any fraction can also be written in
quotient*remainder/divisor format
when solved 48/5
quotient=9
remainder=3
divisor=5
hence,
9*3/5

Ritesh Raj said:   7 years ago
@All.

Check this;
A-16d
B-12d
C-xd.

Lcm of all 3=48x(let it be total work that they have to complete).
Now efficiency ( of A,B,C is 3x,4xand 48 resp)
Now. on 1st day all 3 together can do 3x+4x+48 works it is given that they together complete the work in 4 days so;

4*(3x+4x+48)=48 solve it get x, then you will get the answer.

Palem Ganesh said:   5 years ago
It's quite easy, I will tell the shortcut method.

Take LCM of 16 an 12 is 48 and;
Then find one day work as units.
A = 48/16 = 4.
B = 48/12 = 3.
C = ?.

We know they all together they take just 4 days.
Per day of 4 days work = 48/4 = 12.
A + B + C = 12.
4 + 3 + C = 12.
C = 5.
So, C can do work 5 units per day.
C= 48/5.

Sai kumar Reddy Nossam said:   7 years ago
common multiple for 12 and 16 is 48.

A's one day work =48/16=3 units,
B's one day work=48/12=4 units,
C's one day work??

A and B together do a piece of work in 4 days= 28 units.
remaining work ( C's work in 4 days)=48 - 20 =20 units,
C's work in one day=20/4=5 unit,
C alone can do the job in=(5 * 9)+3/5 = 9 3/5.

Soumya said:   1 decade ago
@Deepika.

C's 1 day work is 5/48.
Here we require C's total work.

Total work should be taken as '1'.

So, 1 day work i.e,5/48*number of days used to complete the work(unknown, so take it as 'x') = total work 1.

Simply, 5/48*x = 1.
5x = 48.
x = 48/5.

So C's total work is 48/5.


Post your comments here:

Your comments will be displayed after verification.