2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 3 of 23.

Deekshit said:   3 years ago
Why the fraction 5/48 is changed to 48/5? Please explain.

Teja said:   3 years ago
A = 16
B = 12.

A + B + C = 4.
16,12,4 LCM = 48.
then,16/48 = 3.
12/48 = 4.
4/48 = 12.
Then,C - (A + B) = 12-(3+4) = 5.
then 48/5.
(5)

Sangmesh said:   4 years ago
5/48 how this came? Please explain.
(1)

Harshal said:   4 years ago
First A=12.
and B=20.

Now the lcm of A and B is 60.
than A and B one day work is 7 and he's work together 7*4=28.
now the 28/60 forestation is 7*15.
and renaming work - total work 28-60=32.
Now 32/60= forestation us 8/15 answer.

Talib said:   4 years ago
A = 16.
B = 12.
A + B + C = 4.

Total work by a, b, c ie LCM of 16, 12, 4 = 48.

Then A work in 1 day = 48/16 = 3unit.
and B work in 1 day = 48/12 = 4 unit.

And A +B+C work in 1 days = 48/4= 12 unit.
Therefore put value of a and b ie 3 + 4 + c = 12.
ie c work in 1 day = 5 unit.
Therefore total work done by C is 48/5 ans simple and fast method.
(3)

St_osagie said:   4 years ago
@All.

Those asking this question: How did come 5/48?

It is called the "rule of flip in time and work" which is how efficiency in piece is derived. Eg. If it takes 3 days for tom to perform a given task. Tom's efficiency in piece is 1/3.
(1)

Nahida Naaz said:   4 years ago
A -> 16
B -> 12.

Lcm -> 48.

Effi 3 and 4.
4 days work of (A+B) :- 4*7 = 28.
Total work - 4 days work of (A+B).
48- 28= 20.

Remaining work of 'C' will do in 4 days
So , 20/4 = 5.
Hence,
Whole work done by 'C'. 48/5.

Gunjan said:   4 years ago
Agree @Truptimayee Bahinipati.

A=15 days.
B= 20 days.



Then the addition of 1/15 + 1/20 =7/60.

7/60 x 4 = 28/60, 28/60 = 14/30, 14/30 = 7/15.
[ 1- 7/15 ] = 8/15.
Answer = 8/15.

Gunjan said:   4 years ago
A-15.
B-20.

1/15 + 1/20 = 7/60.
7/60 x 4= 28/60 = 14/30 = 7/15.
( 1 - 7/15 ) = 8/15.

Disha said:   4 years ago
5/48 of the whole work is done in one day. Then one whole work is;
5/48:1::1:x.
1*1/[5/48] = 48/5.