2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
226 comments Page 2 of 23.

Shivaji said:   2 years ago
Simple logic;

A-----> 16 days.
B ----> 12days.

with the help of C.
AB+C -----> 4 days.

Total work (LCM) = 48.
Efficiency = A--3, B--4, AB+C--12.
A+B = 7,
AB+C = 12
Then C = 12-7 = 5.
C can do work in = Total work/Efficiency = 48/5 = 9*3/5.
(56)

Rahul Kapoor said:   2 years ago
A work done in 16 days.
B work done in 12 days.

A, B and C work done 4 days.

Total work 16,12,4.
Total work 48.

Efficiency of A 48/16 = 3
Efficiency of B 48/13 = 4
Efficiency of A+B+C = 48/4 = 12.
Efficiency of C = 12 - 4 - 3 = 5.
C completed the work alone =48/5.
(105)

RAMAKRISHNA MACHARLA said:   3 years ago
A = 1/16.
B = 1/12.
A+B+C = 1/4.
1/16 + 1/12 + C = 1/4
C = 1/4 - 1/16 - 1/12
C = 5/48 = 48/5.
C = 9 * 3/5.
(99)

Ion Strait said:   3 years ago
The reason that 5/48 becomes 48/5 is that C's one day work = 5/48.
Here it means, the total work in units is 48 and out of that C does 5 units of work in 1 day, so it's 5/48.
But the question asks the time required for C alone to complete the work.
Since, 48 units are the total work, just divide it by the one-day unit of C's work, that is, 5
So, 48/5.
(51)

Tarun kumar agrawal said:   3 years ago
Given that;
A complete the work in --> 16 days.
B complete the work in --> 12 days.
With the help of C (A+B+C) complete the work in --> 4 days.
We take LCM OF (16,12,4) comes --> 48 unit.
A complete --> 48/16 = 3 unit per day.
B complete --> 48/12 = 4 unit per day.
A+B+C complete --> 48/4 = 12 unit per day.
C alone do --> 12-3-4 = 5 unit per day.
so C take time to complete the work in days = total unit/unit per day by c.
= 48/5.
= 9(3/5) days.
When we divided 48 by 5 quotient comes to 9 and the remainder is 3 . it is a mixed fraction.
(122)

SHAILESH SALVE said:   3 years ago
How 5/48 to 48/5? Please explain this step.
(24)

A SANTHI said:   3 years ago
A - 16 Days.
B - 12 days.
A + B + C - 4 days.

We know A and B's one day work - 1/16 and 1/12.

Therefore, Add A+B = 1/16+1/12 (Take LCM).
= 7/48( Which is the one day work for A+B).

We know A+B+C's one-day work = 1/4.
So, A+B+C= 1/4,
7/48+C= 1/4, ( A+B= 7/48 )
C= 1/4 - 7/48 (Take LCM).
C= 5/48 (One day work).

Therefore C's Work = 48/5 (Just inverse of one day),
C= 9 * 3/5.
(20)

Rickykerketta said:   3 years ago
A --- 15.
B --- 20.

We took LCM -- 60.
15 * 4 = 60.
20 * 3 = 60.

Work done = 4 days * 7 = 28 units of work.
60 - 28 = 32,
Part left = 32/60,
8/32.
(5)

Vaishnavi Deshpande said:   3 years ago
Why do not we consider work done by A+B in 4 days and then subtract it from 1 to get work done by C in 4 days? Please anyone explain me.
(2)

Dibyanshu said:   3 years ago
@Nil.

It's a fractional rule.

48/5 = 9+3/5.
Let me explain.

=> 5x9 = 45
So, you can say the reminder a numerator and the denominator is also a denominator.
The reminder is 3 and the Denominator is 5.

So, 9*3/5..
(6)