Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Answer: Option
Explanation:
(A + B + C)'s 1 day's work = | 1 | , |
4 |
A's 1 day's work = | 1 | , |
16 |
B's 1 day's work = | 1 | . |
12 |
![]() |
1 | - | ![]() |
1 | + | 1 | ![]() |
= | ![]() |
1 | - | 7 | ![]() |
= | 5 | . |
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
Discussion:
224 comments Page 14 of 23.
Ganesh said:
10 years ago
Total work is 48 units.
A can do work in 16 days.
It means A completes 3 units per day.
B can do work in 12 days.
It means B completes 4 units per day.
Now A and B is helped by C and completed work in 4 days.
It means A, B and C together doing 12 units per day.
It means A+B+C = 12.
Sub A and B values.
3+4+C = 12.
C = 5.
It means C completes 5 units per day.
For 48 units?
Answer: 48/5.
A can do work in 16 days.
It means A completes 3 units per day.
B can do work in 12 days.
It means B completes 4 units per day.
Now A and B is helped by C and completed work in 4 days.
It means A, B and C together doing 12 units per day.
It means A+B+C = 12.
Sub A and B values.
3+4+C = 12.
C = 5.
It means C completes 5 units per day.
For 48 units?
Answer: 48/5.
(1)
Mathivanan said:
10 years ago
Awesome answers the way of explaining is very excellent. Thank you all of you.
Sidhartha said:
9 years ago
How it come 5/48? Please give a clear solution.
Sudhanshu patra said:
9 years ago
@Ganesh.
Thanks for explaining the answer.
Thanks for explaining the answer.
Sankalp said:
9 years ago
Hi, I have a doubt. Please clarify it.
After finding LCM why do we reverse the answer? (i.e why do we have 48/5 after getting LCM as 5/48).
After finding LCM why do we reverse the answer? (i.e why do we have 48/5 after getting LCM as 5/48).
Shweta Narkhede said:
9 years ago
Thank you very much friends, I got lots of help because of yours discussion with this topic.
Amogh said:
9 years ago
A can complete 1/16th of the work in 1 day.
B can complete 1/12th of the work in 1 day.
Let C complete 1/Xth of the work in 1 day.
So, A, B & C can complete (1/16 + 1/12 + 1/X)th part of the work in 1 day.
Therefore in 4 days, they together can complete = 4*(1/16 + 1/12 + 1/X)th part of the work . Always remember & denote work completed as 1.
On solving 4*(1/16 + 1/12 + 1/X) = 1, you can get the value of x which is the number of days taken by C to do the work.
Hope it helps you.
B can complete 1/12th of the work in 1 day.
Let C complete 1/Xth of the work in 1 day.
So, A, B & C can complete (1/16 + 1/12 + 1/X)th part of the work in 1 day.
Therefore in 4 days, they together can complete = 4*(1/16 + 1/12 + 1/X)th part of the work . Always remember & denote work completed as 1.
On solving 4*(1/16 + 1/12 + 1/X) = 1, you can get the value of x which is the number of days taken by C to do the work.
Hope it helps you.
Sunny said:
9 years ago
A's efficiency = 3, and B's efficiency =4, so (3 + 4) = 5 then C's efficiency (12 - 7) =5, So total work take LCM of (16, 12, 4) = 48, so C alone finished the work 48/5.
Asshok007 said:
9 years ago
@Shantanu
Thank you, you are right.
Actually, A can solve in 16 days for one day it will be 1/16. if we take for 2 days work it will become 2/16. in the same way the work done by c per day is 5/48. If you want total work done by 'c' just reverse the fraction like 48/5.
Ex: THE TOTAL WORK DONE BY 'B' IS IN 12DAYS, FOR ONE DAY 12,IN THE SCENE 12/1. You should remember that 5/48 is the work done by 'c' in one day.
Thank you, you are right.
Actually, A can solve in 16 days for one day it will be 1/16. if we take for 2 days work it will become 2/16. in the same way the work done by c per day is 5/48. If you want total work done by 'c' just reverse the fraction like 48/5.
Ex: THE TOTAL WORK DONE BY 'B' IS IN 12DAYS, FOR ONE DAY 12,IN THE SCENE 12/1. You should remember that 5/48 is the work done by 'c' in one day.
Lakshmi said:
9 years ago
Thanks for clarifying the solution @Ajay.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers