Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 12)
12.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
35
40
45
50
Answer: Option
Explanation:

Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.

Then, 4x + 6y = 1 and 3x + 7y = 1 .
8 10

Solving the two equations, we get: x = 11 , y = 1
400 400

1 woman's 1 day's work = 1 .
400

10 women's 1 day's work = 1 x 10 = 1 .
400 40

Hence, 10 women will complete the work in 40 days.

Discussion:
106 comments Page 8 of 11.

Jayalakshmi said:   1 decade ago
Can you please explain.

How comes.

4x + 6y = 1/8 and 3x + 7y = 1/10.

X = 11/400, y = 1/400.

In easy method above mentioned methods are very difficult to understand.

Afia Sharmin said:   1 decade ago
Answer for: 6 men and 8 women can do a work in 18 days. How many days will it require to complete the whole work if 3 men and 5 women work together?

Ami said:   1 decade ago
4x+6y=1/8 ----(1)
3x+7y=1/10 ----(2)
now,multiply equation 1 with 3 and equ.2 with 4

12x+18y=3/8
12x+28y=2/5
- - -
-------------
-10y=-1/40
10y=1/40 so, 40 become ans

Srinivas said:   1 decade ago
4x+6y=1/8.

3x+7y=1/10.

Here why you are taking days 1/10 and 1/8?

You mean members=1/days ?

MOHAMED SALEEM said:   1 decade ago
Let us sahre CHAN HOW 1 BECOMES 30/8

32x + 48y = 1 --(1) ----> (1) * 30
960x+1440y=30/8 (since 30*32 =960)

Adithi said:   1 decade ago
4 men + 6 Women completes 1/8 of the work
i.e., 4m + 6w = 1/8 --- equation I

3 men + 7women completes 1/10 of the work
i.e ., 3m + 7w = 1/10 --- equation II

Multiply Equation I*3 and Equation II * 4 we get
12m + 18w =3/8
12m + 28w =4/10 ( now subtract)
------------------------------
0 + 10 w = 3/8 -4/10 = 1/40
------------------------------
hence 10 women takes 40 days !

Katam brahmareddy said:   1 decade ago
4x + 6y =1/8*3 and 3x + 7y =1/10*4
12x+18y=3/8 and 12x+28y=2/5
subtract them
12x+18y-3/8-12x-28y+2/5=0
ofter
-10y=-3/8+2/5
=-15+16/40
=1/40 (it is work done for day with ten womens)
-10y=1/40*10
=1/40
answer is 40 days..

Prasant said:   1 decade ago
4x+6y = 1/8
=> 4x+6/400 = 1/8 ...as x=1/400
=> 4x = 1/8-6/400
=> 4x = 11/100
=> x = 11/400

Kalyan said:   1 decade ago
Hi can any body say how 11/400 is possible?

Nira said:   1 decade ago
How we get 8*50w=10w?


Post your comments here:

Your comments will be displayed after verification.