Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 4 of 36.
Veda said:
1 decade ago
"A" can complete work in 20 days.
A's 1 day work is 1/20.
A's 2 days work is 2/20.
According to the question A work for 2 day's and on the third day.
B & C assists (**helps, not replaced).
So it goes like this.
A's first day + A's second day + (A + B + C) on third day, B & C helped.
i.e 2 1/20+1/20/+(1/20+1/30+1/60).
=>2/20+(1/20+1/30+1/60).
=>2/20+1/10.
= 1/5.
So for first 2 days and combining B and C on third day they will work 1/5th of a work.
All together (A+A+ (A+B+C) ) works for 3 days to get 1/5th of a work so.
If 1/n work is done in 1 days total work is done in 1*n = n days.
The same here, if 1/5 work is done in 3 days total work is done in 5*3 = 15 days.
A's 1 day work is 1/20.
A's 2 days work is 2/20.
According to the question A work for 2 day's and on the third day.
B & C assists (**helps, not replaced).
So it goes like this.
A's first day + A's second day + (A + B + C) on third day, B & C helped.
i.e 2 1/20+1/20/+(1/20+1/30+1/60).
=>2/20+(1/20+1/30+1/60).
=>2/20+1/10.
= 1/5.
So for first 2 days and combining B and C on third day they will work 1/5th of a work.
All together (A+A+ (A+B+C) ) works for 3 days to get 1/5th of a work so.
If 1/n work is done in 1 days total work is done in 1*n = n days.
The same here, if 1/5 work is done in 3 days total work is done in 5*3 = 15 days.
(1)
B SUNDARA said:
8 years ago
Since B and C assisting A on every 3rd day, B & C takes 30x3=90 days and 60x3=180 days respectively to do the work.
Therefore
1/20+1/90+1/180 = 12/180 = 1/15 or 15 days.
Therefore
1/20+1/90+1/180 = 12/180 = 1/15 or 15 days.
(1)
Abdullah Shaikh said:
8 years ago
LCM method:
The LCM of A,B,C is 60 so consider total work to be 60 unit.
Since A take 20 days, he does 3 unit per day.
Similarly, B does 2 unit per day.
Similarly, C does 1 unit per day.
So total unit of work done by 3 combined is 6 unit.
So by Addition of each day of Unit of work done until reaching total work. So the addition of A alone and A+B+C can be summarized as.
A doing work for first 2 days will be 2*3, total Work 6 done.
On 3rd day work done is 6, total work done 12.
Again A working alone for 4th and 5th is 2*3 =6,
Total work 18
On 6th day work done (A+B+C) 6, Total work 24
On 7th and 8th A is 6, total work 30.
On 9th day again (A+B+C) work done 6, TOTAL 36.
On 10 and 11th A alone work was done 6, Total work 42.
On 12th (A+B+C) work done 6, Total work 48.
On 13 and 24th A alone is 6, Total work 54.
On 15th A+B+C is 6, Total work was done 60 unit, work completed.
The LCM of A,B,C is 60 so consider total work to be 60 unit.
Since A take 20 days, he does 3 unit per day.
Similarly, B does 2 unit per day.
Similarly, C does 1 unit per day.
So total unit of work done by 3 combined is 6 unit.
So by Addition of each day of Unit of work done until reaching total work. So the addition of A alone and A+B+C can be summarized as.
A doing work for first 2 days will be 2*3, total Work 6 done.
On 3rd day work done is 6, total work done 12.
Again A working alone for 4th and 5th is 2*3 =6,
Total work 18
On 6th day work done (A+B+C) 6, Total work 24
On 7th and 8th A is 6, total work 30.
On 9th day again (A+B+C) work done 6, TOTAL 36.
On 10 and 11th A alone work was done 6, Total work 42.
On 12th (A+B+C) work done 6, Total work 48.
On 13 and 24th A alone is 6, Total work 54.
On 15th A+B+C is 6, Total work was done 60 unit, work completed.
(1)
Gabriel said:
6 years ago
One simple way : 1/20 + (1/90 + 1/180) = 1/15.
(1)
Poonam said:
5 years ago
Here is a solution:
Efficiency A = 3 , B = 2, C = 1 and A+B+C = 6.
Now,
Work done in format ie A can do a work in 2day and next 1day with B&c .
So.
Eff * time = work.
A = 3 * 2 = 6.
A + B + C = 6 * 1 = 6.
Means work done in 3 days is 6 + 6 = 12 work.
Days -------- work
3 -------- 12
? ------- 60 (total work)
Days =(60*3) / 12.
The answer is = 15 days.
Efficiency A = 3 , B = 2, C = 1 and A+B+C = 6.
Now,
Work done in format ie A can do a work in 2day and next 1day with B&c .
So.
Eff * time = work.
A = 3 * 2 = 6.
A + B + C = 6 * 1 = 6.
Means work done in 3 days is 6 + 6 = 12 work.
Days -------- work
3 -------- 12
? ------- 60 (total work)
Days =(60*3) / 12.
The answer is = 15 days.
(1)
Hrishi said:
5 years ago
Step 1: Work is done by A+B+C in one day can be calculated as 1/20 + 1/30 + 1/60 = 1/10.
Step 2: For the first two days only A is doing work alone so the work is done by A in two days will be 2*1/20= 1/10.
Step 3: Now total work is done in 3 days by A B & C will be = 1/10+1/10= 1/5.
Step 4: But we need a complete work to be done so we have to convert 1/5 to 1 therefore if we do 1/5 work 5 times then work will be completed (1/5 x 5=1).
Therefore 5 x 3 = 15.
Hope you will understand this solution.
Step 2: For the first two days only A is doing work alone so the work is done by A in two days will be 2*1/20= 1/10.
Step 3: Now total work is done in 3 days by A B & C will be = 1/10+1/10= 1/5.
Step 4: But we need a complete work to be done so we have to convert 1/5 to 1 therefore if we do 1/5 work 5 times then work will be completed (1/5 x 5=1).
Therefore 5 x 3 = 15.
Hope you will understand this solution.
(1)
Britney said:
5 years ago
How did we get 6/60? Anyone explain about it.
(1)
Sunil_ said:
5 years ago
A work in one day = 1/20,
B work in one day = 1/30,
C work in one day = 1/60.
As A work for 2 days and then on third day B and C do work.
Total work done in three days = A 3 days work+B 1-day work+ C one day work,
= 3/20 + 1/30 + 1/60,
= 9/60 + 2/60 + 1/60
= 12/60.
Total work is done in three days =1/5.
3 = 1/5part.
Let x days required to complete work = 1 part.
3/x = 1/5/1.
x = 3 * 5 = 15 days.
B work in one day = 1/30,
C work in one day = 1/60.
As A work for 2 days and then on third day B and C do work.
Total work done in three days = A 3 days work+B 1-day work+ C one day work,
= 3/20 + 1/30 + 1/60,
= 9/60 + 2/60 + 1/60
= 12/60.
Total work is done in three days =1/5.
3 = 1/5part.
Let x days required to complete work = 1 part.
3/x = 1/5/1.
x = 3 * 5 = 15 days.
(1)
Vijay said:
5 years ago
How we got only A done 3 days of work? Please explain it.
(1)
T.S said:
5 years ago
@Vijay
We know that the whole work done is 1. here 3 days work is 1/5.
So,
if, 1/5 work=3days.
then, 1 work= ?
Cross multiply we get ?= 3 x 5= 15days.
We know that the whole work done is 1. here 3 days work is 1/5.
So,
if, 1/5 work=3days.
then, 1 work= ?
Cross multiply we get ?= 3 x 5= 15days.
(1)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers