Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 3 of 36.
Vikas said:
1 decade ago
Answer Explained:
A is working alone for two days, 3rd day he is assisted by B and C.
A's 1 day work=1/20
A working on 2 days=2*1/20=1/10
A+B+C working on 3rd day, so 1 day of working together=1/20+1/30+1/60=6/60=1/10
So total work done till 3rd day=1/10+1/10=2/10=1/5
So if in 3 days = 1/5 of work is completed....
Than, 3*5 days = 1/5*5 work will be completed.
=15days
A is working alone for two days, 3rd day he is assisted by B and C.
A's 1 day work=1/20
A working on 2 days=2*1/20=1/10
A+B+C working on 3rd day, so 1 day of working together=1/20+1/30+1/60=6/60=1/10
So total work done till 3rd day=1/10+1/10=2/10=1/5
So if in 3 days = 1/5 of work is completed....
Than, 3*5 days = 1/5*5 work will be completed.
=15days
(4)
Usman said:
5 years ago
Solution:
A do a piece of work in = 1/20 days.
'A' work alone for 2 days, so the work done by A on the second day is = 2/20 = 1/10
On the third day, A is assisted by B&C, then the work done by three of them is = 1/10 + 1/20 + 1/30 = 3/20.
Total work done by A in 3 days is = 1/20 + 3/20 = 1/5.
As we have to find number of days, so,
1/5 part of work done by A is in = 3 days.
1 part of the work done by A is in = 3x5 = 15 days.
In 15 days, A can do the work if he is assisted by B& C on the third day.
A do a piece of work in = 1/20 days.
'A' work alone for 2 days, so the work done by A on the second day is = 2/20 = 1/10
On the third day, A is assisted by B&C, then the work done by three of them is = 1/10 + 1/20 + 1/30 = 3/20.
Total work done by A in 3 days is = 1/20 + 3/20 = 1/5.
As we have to find number of days, so,
1/5 part of work done by A is in = 3 days.
1 part of the work done by A is in = 3x5 = 15 days.
In 15 days, A can do the work if he is assisted by B& C on the third day.
(4)
Poojitha said:
4 years ago
@Dhanam.
Because on third day they are doing combined work it means that for 1st 2 days they have worked alone here in question. About A has asked so he is doing only A.
Because on third day they are doing combined work it means that for 1st 2 days they have worked alone here in question. About A has asked so he is doing only A.
(3)
V.MADANKUMAR said:
1 decade ago
A's 2 day's work = (1/20x2) = 1/10.
(A + B + C)'s 1 day's work = [(1/20)+(1/30)+(1/60)] = 6/60 = 1/10.
Work done in 3 days = [(1/10)+(1/10)] = 1/5.
Now what they ask "How many days can "A" do the work?"
Here revise the FORMULA NO:2.
That is:
Days from Work:
If A's 1 day's work =1/n,then A can finish the work in n days.
Here ===> [1 DAY's work = NO.of WORK / required "n" Day's do the work ].
We want no.of DAY's;
So rearrange the formula; we get,
No.of WORK = (1DAY's work * "n" DAY's) ------> take eqn no.1.
Now, (1/5) work is done in 3 days.
3 = 1/5.
So apply above the data's in eqn no.1.
1(No.of Work) = (Day's of Work )3 * ("n" DAY's)5.
1(No.of Work) = 15 Day's
So "A" is require 15 Day's to do a 1 work.
"I HOPE U WILL B UNDERSTAND"
(A + B + C)'s 1 day's work = [(1/20)+(1/30)+(1/60)] = 6/60 = 1/10.
Work done in 3 days = [(1/10)+(1/10)] = 1/5.
Now what they ask "How many days can "A" do the work?"
Here revise the FORMULA NO:2.
That is:
Days from Work:
If A's 1 day's work =1/n,then A can finish the work in n days.
Here ===> [1 DAY's work = NO.of WORK / required "n" Day's do the work ].
We want no.of DAY's;
So rearrange the formula; we get,
No.of WORK = (1DAY's work * "n" DAY's) ------> take eqn no.1.
Now, (1/5) work is done in 3 days.
3 = 1/5.
So apply above the data's in eqn no.1.
1(No.of Work) = (Day's of Work )3 * ("n" DAY's)5.
1(No.of Work) = 15 Day's
So "A" is require 15 Day's to do a 1 work.
"I HOPE U WILL B UNDERSTAND"
(2)
Vinoth said:
2 decades ago
How do you know total working day is 3 (last step).
(1)
Satyendra Sharma said:
2 decades ago
3 days work = 1/5
it means 1 day work =1/15
that is 1/15 work is done in 1 Day
now 4/5 part of work that is (1-1/5) will be done in :15*4/5 =12 days....
Hence total work done will done in (12 + 3 ) days...
it means 1 day work =1/15
that is 1/15 work is done in 1 Day
now 4/5 part of work that is (1-1/5) will be done in :15*4/5 =12 days....
Hence total work done will done in (12 + 3 ) days...
(1)
Nikita Prasad said:
1 decade ago
There's a simple logic friends,
If a person wrks for n days, his 1 day's work is 1/n.
or the other way round,
if 1/n is the 1 day's work then he works for n days.
& it can be very well known if 1 day's work is known it can be multiplied with any numbers of days you wish to.
Similarely,
Here last statement tell the same i.e. 3days work is 1/5,
so to calculate 1 day's work we need to divide it by 3 wiz gives 1/15.
so if 1/15 is 1 day's work then they together work for 15 days.
& the logic behind 2 days & 3 dats work is :
A's 2 days work is (1/20)*2, i.e 1 day's multiplied by nth day.
but on the "3rd day" they all A,B&C work together wiz equals to 1/10.
Therefore 2 days + 3rd day's wrk gives 3 day's work.
If a person wrks for n days, his 1 day's work is 1/n.
or the other way round,
if 1/n is the 1 day's work then he works for n days.
& it can be very well known if 1 day's work is known it can be multiplied with any numbers of days you wish to.
Similarely,
Here last statement tell the same i.e. 3days work is 1/5,
so to calculate 1 day's work we need to divide it by 3 wiz gives 1/15.
so if 1/15 is 1 day's work then they together work for 15 days.
& the logic behind 2 days & 3 dats work is :
A's 2 days work is (1/20)*2, i.e 1 day's multiplied by nth day.
but on the "3rd day" they all A,B&C work together wiz equals to 1/10.
Therefore 2 days + 3rd day's wrk gives 3 day's work.
(1)
Benny said:
1 decade ago
Here my simple ans:
A is working continue 2 day's.So he's 2day's work is:1/20*2=1/10;
in 3rd day he join other two person B and C.So here 3 member work:
1/20+1/30+1/60=1/10;
3 day's work is :1/0+1/10=1/5
So total work done by them is 10+5=15;
A is working continue 2 day's.So he's 2day's work is:1/20*2=1/10;
in 3rd day he join other two person B and C.So here 3 member work:
1/20+1/30+1/60=1/10;
3 day's work is :1/0+1/10=1/5
So total work done by them is 10+5=15;
(1)
Manoj said:
1 decade ago
i.e;
3 days =1/5
6 days=2/5
9 days=3/5
12 days=4/5
15 days=5/5(1)==work completed
3 days =1/5
6 days=2/5
9 days=3/5
12 days=4/5
15 days=5/5(1)==work completed
(1)
Raman(UIET,KUK) said:
1 decade ago
Guys check dis out........
as we know A will be assist by B & C every third day, so first two day A will work again
A's 1st day of work = 1/20
A's 2nd day of work = 1/20
(A+B+C)'s 3rd day of work = 1/20+1/30+1/60=1/10
total work of 3 days = 1/20+1/20+1/10=1/5
hence,
3 days of work = 1/5
1 day of work will be=1/5*3
=1/15
so work will complete in 15 days
as we know A will be assist by B & C every third day, so first two day A will work again
A's 1st day of work = 1/20
A's 2nd day of work = 1/20
(A+B+C)'s 3rd day of work = 1/20+1/30+1/60=1/10
total work of 3 days = 1/20+1/20+1/10=1/5
hence,
3 days of work = 1/5
1 day of work will be=1/5*3
=1/15
so work will complete in 15 days
(1)