Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 36 of 36.
Mohammed said:
9 years ago
Why here they take 2?
Ajit said:
1 decade ago
Why multiply 1/20*2?
Bala said:
1 decade ago
I can't get this.
Salman said:
8 years ago
How 6/60 come?
Anil said:
1 decade ago
Thanks benny.
Mamun said:
7 years ago
Thanks all.
Manoj shukla said:
1 decade ago
Why 3*5?
Post your comments here: