Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 34 of 36.
Vijay said:
5 years ago
How we got only A done 3 days of work? Please explain it.
(1)
T.S said:
5 years ago
@Vijay
We know that the whole work done is 1. here 3 days work is 1/5.
So,
if, 1/5 work=3days.
then, 1 work= ?
Cross multiply we get ?= 3 x 5= 15days.
We know that the whole work done is 1. here 3 days work is 1/5.
So,
if, 1/5 work=3days.
then, 1 work= ?
Cross multiply we get ?= 3 x 5= 15days.
(1)
Amit bhau said:
4 years ago
3 days ---> work 1/5
x days ---> to get total work =1
Cross multiplication, then we get x = 15.
x days ---> to get total work =1
Cross multiplication, then we get x = 15.
(1)
Disha said:
4 years ago
Every 3 days 1/5 work is done. Then in how many days 1 whole work is done.
Mathematically = 1/5:3::1:x.
3*1/ (1/5) = 3÷1/5= 3*5/1= 3*5= 15.
Mathematically = 1/5:3::1:x.
3*1/ (1/5) = 3÷1/5= 3*5/1= 3*5= 15.
Kiran said:
4 years ago
Hi, can anyone tell me what's wrong here?
Given,
A=20days.
B=30days.
C=60days.
I took as 60units of work by taking LCM of A, B, C.
A's one day work=3 units/day.
B's one day work=2 units/day.
A's two days work = 6 units.
B's one day work= 2 units.
C's one day work= 1 unit.
A+B+C's 3 days work = 9 units.
So, I can take A+B+C's one day work = 3 units =>9/3=3 units/day.
So, to complete 60 units of work they will take 20days =>20*3=60 units.
So, I am saying that answer is "20 days".
Correct me if I'm wrong.
Given,
A=20days.
B=30days.
C=60days.
I took as 60units of work by taking LCM of A, B, C.
A's one day work=3 units/day.
B's one day work=2 units/day.
A's two days work = 6 units.
B's one day work= 2 units.
C's one day work= 1 unit.
A+B+C's 3 days work = 9 units.
So, I can take A+B+C's one day work = 3 units =>9/3=3 units/day.
So, to complete 60 units of work they will take 20days =>20*3=60 units.
So, I am saying that answer is "20 days".
Correct me if I'm wrong.
(1)
Sairam said:
4 years ago
@Kiran.
You didn't account for A's third day of work.
A does 6 units of work in two days and another 3 units on the third day. So in total, A has done 9 units of work in 3 days.
You didn't account for A's third day of work.
A does 6 units of work in two days and another 3 units on the third day. So in total, A has done 9 units of work in 3 days.
(1)
Poojitha said:
4 years ago
@Dhanam.
Because on third day they are doing combined work it means that for 1st 2 days they have worked alone here in question. About A has asked so he is doing only A.
Because on third day they are doing combined work it means that for 1st 2 days they have worked alone here in question. About A has asked so he is doing only A.
(3)
Ananthu said:
4 years ago
For the peopel who are confused with last step.
We knew that 3 days work is 1/5.. the remaining work is 1-1/5=4/5.. ie already worked 3 days here.
Then we are calculating that how many 3 days are required to complete the remaining work 4/5.
Ie 4/5/1/5 = 4/5 * 5/1 = 4.. 4 (three days required).
ie 4*3 = 12 we already worked 3 days then total days will be 12 + 3 = 15.
We knew that 3 days work is 1/5.. the remaining work is 1-1/5=4/5.. ie already worked 3 days here.
Then we are calculating that how many 3 days are required to complete the remaining work 4/5.
Ie 4/5/1/5 = 4/5 * 5/1 = 4.. 4 (three days required).
ie 4*3 = 12 we already worked 3 days then total days will be 12 + 3 = 15.
(8)
Piyush chandana said:
4 years ago
Mem ------> time ---- efficiency ----work
a------> 20 ---- 3 ---- 60
b------> 30 ---- 2 ---- 60
c------> 60 ---- 1 ---- 60
Now we make a series like :-
Day1 total unit of work will be -> 3 units.
Day2 total unit of work will be-> 3 units.
Day3 total unit of work will be -> 3+1+2 = 6(because b and c helped him).
Day1 Day2 Day3
3 3 6.
Work will be-> 12 units = 3 days.
The total units of work is 60 units then divide 60 with 12(60/12=5).
Now the total units are 5 times the 3 days of work than days will also multiply by 5 which is 3*5="15 days" (Ans).
a------> 20 ---- 3 ---- 60
b------> 30 ---- 2 ---- 60
c------> 60 ---- 1 ---- 60
Now we make a series like :-
Day1 total unit of work will be -> 3 units.
Day2 total unit of work will be-> 3 units.
Day3 total unit of work will be -> 3+1+2 = 6(because b and c helped him).
Day1 Day2 Day3
3 3 6.
Work will be-> 12 units = 3 days.
The total units of work is 60 units then divide 60 with 12(60/12=5).
Now the total units are 5 times the 3 days of work than days will also multiply by 5 which is 3*5="15 days" (Ans).
(18)
Aayush PAndey said:
4 years ago
A. B. C. Take => a=20, b=3, c=60 days respectively.
The Lcm of 20, 30, 60 is 60.
So the efficiency of a, b, c is :.
Eff days.
3<---a---20---->.
2<---b---30---->
1<---c---60---->.
And 60 (total work).
Now work done by A in 2 days will be => 3*3 = 6.
On the 3rd day a, b, c will work so Work done will be = 3+2+1 = 6.
Work done in 3 days = 6+6 =12.
So, (12 work) is done in 3 days,
(1 work) will be done in = 3/12 days.
(total work is 60) , will be done in = (3/12) *60 = 60/4 = 15 days.
The Lcm of 20, 30, 60 is 60.
So the efficiency of a, b, c is :.
Eff days.
3<---a---20---->.
2<---b---30---->
1<---c---60---->.
And 60 (total work).
Now work done by A in 2 days will be => 3*3 = 6.
On the 3rd day a, b, c will work so Work done will be = 3+2+1 = 6.
Work done in 3 days = 6+6 =12.
So, (12 work) is done in 3 days,
(1 work) will be done in = 3/12 days.
(total work is 60) , will be done in = (3/12) *60 = 60/4 = 15 days.
(32)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers