Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 33 of 36.
Keerthi said:
5 years ago
why are we multiplying 1/5 *3 in the last step? Please explain anyone.
Kanishk said:
5 years ago
@Keerthi.
We are not directly multiplying.
We just use the unitary method. Here the total work done is 1. In fact, in all these sums total work is 1.
Now,
Since 1/5th of the work is done in 3 days,
Therefore, 1 of the work( whole work) is done in 3*5 days.
Hope you understand.
We are not directly multiplying.
We just use the unitary method. Here the total work done is 1. In fact, in all these sums total work is 1.
Now,
Since 1/5th of the work is done in 3 days,
Therefore, 1 of the work( whole work) is done in 3*5 days.
Hope you understand.
Pooja Pawatekar said:
5 years ago
How can you take A's 2 days work? Can anyone explain this pls?
Avinash Singh said:
5 years ago
Here's an easy one:
Let's assume that the total work is done in x days.
Then x/3 days, A will require B and C's help and 2x/3 days A will be working alone.
So the equation becomes:
x/3(1/20) + 2x/3(1/20 + 1/30 + 1/60) = 1 [1 because 1 unit of work is done in x days].
Solve it and you'll get x = 15. Thanks!
Let's assume that the total work is done in x days.
Then x/3 days, A will require B and C's help and 2x/3 days A will be working alone.
So the equation becomes:
x/3(1/20) + 2x/3(1/20 + 1/30 + 1/60) = 1 [1 because 1 unit of work is done in x days].
Solve it and you'll get x = 15. Thanks!
Britney said:
5 years ago
How did we get 6/60? Anyone explain about it.
(1)
Yoezer said:
5 years ago
3 days 1/5.
6 days 2/5.
9 days 3/5.
12 days 4/5.
15 days 5/5( work completed).
6 days 2/5.
9 days 3/5.
12 days 4/5.
15 days 5/5( work completed).
Sunil_ said:
5 years ago
A work in one day = 1/20,
B work in one day = 1/30,
C work in one day = 1/60.
As A work for 2 days and then on third day B and C do work.
Total work done in three days = A 3 days work+B 1-day work+ C one day work,
= 3/20 + 1/30 + 1/60,
= 9/60 + 2/60 + 1/60
= 12/60.
Total work is done in three days =1/5.
3 = 1/5part.
Let x days required to complete work = 1 part.
3/x = 1/5/1.
x = 3 * 5 = 15 days.
B work in one day = 1/30,
C work in one day = 1/60.
As A work for 2 days and then on third day B and C do work.
Total work done in three days = A 3 days work+B 1-day work+ C one day work,
= 3/20 + 1/30 + 1/60,
= 9/60 + 2/60 + 1/60
= 12/60.
Total work is done in three days =1/5.
3 = 1/5part.
Let x days required to complete work = 1 part.
3/x = 1/5/1.
x = 3 * 5 = 15 days.
(1)
Arun said:
5 years ago
Worker - TotalDay - OneDay
A - 20 - 1/20
B - 30 - 1/30
C - 60 - 1/60
1st Day - A.
2nd Day- B.
3rd Day - A, B, C.
They said A lonely can work for 2 day.
2A = 2(1/20) =1/10.
Then in third day A, B, C together;
(A+B+C) = 1/20+1/30+1/60,
= 1/10.
3 Days(not 3rd Day) work is;
=2A + (A+B+C).
= 1/10+1/10.
3Days =1/5 work,
6Days =2/5 work,
9Days =3/5 work,
12Days=4/5 work,
15Days= 5/5 =1 work completed.
A - 20 - 1/20
B - 30 - 1/30
C - 60 - 1/60
1st Day - A.
2nd Day- B.
3rd Day - A, B, C.
They said A lonely can work for 2 day.
2A = 2(1/20) =1/10.
Then in third day A, B, C together;
(A+B+C) = 1/20+1/30+1/60,
= 1/10.
3 Days(not 3rd Day) work is;
=2A + (A+B+C).
= 1/10+1/10.
3Days =1/5 work,
6Days =2/5 work,
9Days =3/5 work,
12Days=4/5 work,
15Days= 5/5 =1 work completed.
(5)
Abdul moeed said:
5 years ago
Use unity rule at the last step,
1/5 work is done in = 3 days.
1 work (whole work) is done in = 3/1/5 = 3*5= 15 days.
1/5 work is done in = 3 days.
1 work (whole work) is done in = 3/1/5 = 3*5= 15 days.
Usman said:
5 years ago
Solution:
A do a piece of work in = 1/20 days.
'A' work alone for 2 days, so the work done by A on the second day is = 2/20 = 1/10
On the third day, A is assisted by B&C, then the work done by three of them is = 1/10 + 1/20 + 1/30 = 3/20.
Total work done by A in 3 days is = 1/20 + 3/20 = 1/5.
As we have to find number of days, so,
1/5 part of work done by A is in = 3 days.
1 part of the work done by A is in = 3x5 = 15 days.
In 15 days, A can do the work if he is assisted by B& C on the third day.
A do a piece of work in = 1/20 days.
'A' work alone for 2 days, so the work done by A on the second day is = 2/20 = 1/10
On the third day, A is assisted by B&C, then the work done by three of them is = 1/10 + 1/20 + 1/30 = 3/20.
Total work done by A in 3 days is = 1/20 + 3/20 = 1/5.
As we have to find number of days, so,
1/5 part of work done by A is in = 3 days.
1 part of the work done by A is in = 3x5 = 15 days.
In 15 days, A can do the work if he is assisted by B& C on the third day.
(4)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers