3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 34 of 36.

Divya said:   1 decade ago
Chitra its very clear.

Hamsa said:   1 decade ago
How did you get 6/60 could you please clarify?

Rajasekhar said:   1 decade ago
The question does'nt mean to find the 3 days work how we can solve this for 3 days work?.

Poonam said:   1 decade ago
Please give altarnate methad to solve this question, then we know wether the ans you got is right or wrong.

Manasa said:   1 decade ago
@nikita prasad. You just rock. Good explanation with logic. :-) ).

Karan Singh said:   1 decade ago
Is Vijay's formuala correct? In real aptitude test, the quick formula will be handy and faster to calculate.

Karan Singh said:   1 decade ago
Indeed, the explanation of baskar is correct.

Munish said:   1 decade ago
Thank you Vikas for your information, I have understood.

Samathu said:   1 decade ago
Nice explanation baskar.

Baskar said:   1 decade ago
@chitra
assisted by B and C on every third day
it means A's 2 days + (B&C)'s 1 day
from d 1st explanation u got
Work done in 3 days=(1/10 + 1/10)=1/5
dat is in 3 days=1/5 works
in ques dey ask "In how many days can A do the work"
now cross multiply..
(5*3) days=1 work..
1 work = 15 days...
now u got it ah?