Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 22 of 36.

Garima Yadav said:   1 decade ago
I haven't got it. Can anyone please help me for this?

Ranju said:   1 decade ago
(A+B+C)'s 1 day of work is (1/20+1/30+1/60) = 1/10.

A's 2 days of work is (1/20 X 2) = 1/10.

As on the third day A is assisted by B and C.

=> A's 2 days of work + On 3rd day A is assisted by B and C i.e. (A+B+C) 's 1 day of work.

1/10 + 1/10 = 2/10 = 1/5.

As 1/5 part of work is done in 3 days.

Therefore 1 part of work is done in 3 X 5 = 15 days.

Nandha said:   1 decade ago
@Ajit.

A do a work two days independently, so (1/20+1/20) = 1/10 instead of they taken (1/20*2).

Deepti said:   1 decade ago
Its written every 3rd day NOT First 3 days. Therefore the answer is as below:

(A+B+C)'s 1 day work = (1/20 + 1/30 + 1/60) = 1/10.

=> They all take 10 days to complete their work together.

Out of those 10 days, 3th, 6th and 9th are the 3rd days. In total B and C can help A for only 3 days.

Therefore, (A's 1 days work) + (B+C) 1 day work*3 = 1/20 + (1/30+1/60) *3 = 4/20 = 1/5.

If 1/5 is the work in 3 days, Then complete work done = 5*3 = 15.

Ans: 15 days.

Vijay said:   1 decade ago
B and C joined with A for every 3 days.

So their (A,B,C) 3 days work is == (A's 2 days work i.e. [1/10]) + (A+B+C 's 1 day work i.e [1/10]).

= 1/10+1/10 = 1/5.

So for 3 days 1/5 work is done.

So total work will complete in 15 days.

Ajit said:   1 decade ago
Why multiply 1/20*2?

Mir sakib said:   1 decade ago
What is its mean every third day?

Chitra said:   1 decade ago
Work done in 3 days = 1/5.

Work done in next 3 days = 1/5+1/5.

Work done in 5 days = 1/5+1/5+1/5+1/5+1/5 = 5/5 = 1 (task completed).

Hence 3*5 is used.

Golu said:   1 decade ago
Why we are calculating 2 days of work A?

Psyco said:   1 decade ago
1/5th work done in 3 days.
5/5th of work will be done in x days so,

1/5---3.
5/5---x.

x=3*5*5/5.
x=15.


Post your comments here:

Your comments will be displayed after verification.