Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 19 of 36.

Jibinlal said:   10 years ago
1/5 work is done in 3 days. Remaining work is 4/5.

1/5+1/5+1/5+1/5 = 3+3+3+3 = 12 days.

Total = 12 days (4/5th work)+3 days (1/5th work). So 15 days.

Manju verma said:   10 years ago
Thank you for the solution its really easy way to understand.

Mareeswari said:   10 years ago
Sir I can't understand the A is working two days please explain.

Lakhan said:   1 decade ago
Why 3 is multiplied by 5 in first method?

Manisha said:   1 decade ago
Please tell me answer in LCM method.

Narendra patidar said:   1 decade ago
Please clear explain.

Varun said:   1 decade ago
How you can take total working days as 3 in last step?

Satish kumar said:   1 decade ago
How will make step 3 (1/10+1/10) explain?

Vipul said:   1 decade ago
Work of 1 day = 1/20+1/30+1/60= 6/60= 1/10.

It means that 1/10th part of work is done in 1 day.

(It means 10% work per day).

Now every 3rd day B And C performs -ve work i.e,

Work of every 3rd day = 1/20- 1/30-1/60 = 0/60 = 0.

Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14.

Work% 10+10+0+10+10+0+10+10+0+10+10+0+10+10 = 100%.

Hence work will complete in 14 days.

Note: You can consider day 15 because in day 15 the work done will 0%.

So more correct answer will 14 days.

Lallitha said:   1 decade ago
In given question, A is assisted on every 3rd days but you all doing for one 3rd day?

Can anyone explain?


Post your comments here:

Your comments will be displayed after verification.