Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 19 of 36.
Jibinlal said:
10 years ago
1/5 work is done in 3 days. Remaining work is 4/5.
1/5+1/5+1/5+1/5 = 3+3+3+3 = 12 days.
Total = 12 days (4/5th work)+3 days (1/5th work). So 15 days.
1/5+1/5+1/5+1/5 = 3+3+3+3 = 12 days.
Total = 12 days (4/5th work)+3 days (1/5th work). So 15 days.
Manju verma said:
10 years ago
Thank you for the solution its really easy way to understand.
Mareeswari said:
10 years ago
Sir I can't understand the A is working two days please explain.
Lakhan said:
1 decade ago
Why 3 is multiplied by 5 in first method?
Manisha said:
1 decade ago
Please tell me answer in LCM method.
Narendra patidar said:
1 decade ago
Please clear explain.
Varun said:
1 decade ago
How you can take total working days as 3 in last step?
Satish kumar said:
1 decade ago
How will make step 3 (1/10+1/10) explain?
Vipul said:
1 decade ago
Work of 1 day = 1/20+1/30+1/60= 6/60= 1/10.
It means that 1/10th part of work is done in 1 day.
(It means 10% work per day).
Now every 3rd day B And C performs -ve work i.e,
Work of every 3rd day = 1/20- 1/30-1/60 = 0/60 = 0.
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14.
Work% 10+10+0+10+10+0+10+10+0+10+10+0+10+10 = 100%.
Hence work will complete in 14 days.
Note: You can consider day 15 because in day 15 the work done will 0%.
So more correct answer will 14 days.
It means that 1/10th part of work is done in 1 day.
(It means 10% work per day).
Now every 3rd day B And C performs -ve work i.e,
Work of every 3rd day = 1/20- 1/30-1/60 = 0/60 = 0.
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14.
Work% 10+10+0+10+10+0+10+10+0+10+10+0+10+10 = 100%.
Hence work will complete in 14 days.
Note: You can consider day 15 because in day 15 the work done will 0%.
So more correct answer will 14 days.
Lallitha said:
1 decade ago
In given question, A is assisted on every 3rd days but you all doing for one 3rd day?
Can anyone explain?
Can anyone explain?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers