Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 17 of 36.

Shivam said:   10 years ago
Let n be the no. of total days required;

A's one day work = 1/10.

B's = 1/30, C's = 1/60.

So n(1/10)+n/3(1/30+1/60) = 1.

From here, we get n = 15.

Sai said:   1 decade ago
I still can't get clarification.

In the question they asked that in every 3rd day of A's work.

But in explanation how can you say for only 3 days.

Krats said:   1 decade ago
1/5 works is being done in 3 days.

i.e 1 of the 5 parts of work is done in 3 days.

So total there are 5 parts of work which will take 5*3=15 days.

Alan said:   1 decade ago
Work done by A+B+C for 1 day is 1/10.

So work done by them for 3 days should 1/10 + 1/10 + 1/10 = 3/10.

How come its just for 2 days giving 1/5.

Pakiil said:   7 years ago
The work done in 3 days is 1/5.
So the work remaining is 4/5.
1/5=3 days,
2/5=3 days,
3/5=3 days,
4/5= 3 days,
5/5= 3 days,

The total days=15.

Surya said:   8 years ago
Usually, we are taking 20 days means 1/20. Then why there finding 2 days work is multiplied by 2?

My thoughts are 1/20*1/2. Please explain me.

Aaron said:   9 years ago
At the last step 1/5 * 3 we must do reciprocal right?

Or just multiple and get 15 for the sake of the answer in the options. Please tell me.

Disha said:   4 years ago
Every 3 days 1/5 work is done. Then in how many days 1 whole work is done.

Mathematically = 1/5:3::1:x.

3*1/ (1/5) = 3÷1/5= 3*5/1= 3*5= 15.

Karthik said:   1 decade ago
@Preethi.

3*5 because 1/5*5 gives you 1 which means the work has been completed. So 1/5 is derived for work done in 3 days. Understood ah.

Subash said:   9 years ago
In 3 days they work is 1/5;
Then remaining work is 1 - 1/5 = 4/5,

So using proportions 1/5 : 45 :: 3 : x.

Get 12days.

+ 3days = 15days.


Post your comments here:

Your comments will be displayed after verification.