Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 14 of 36.

Priti said:   1 decade ago
We have already calculate 1/5 for 3 days. Then why again multiplying by 3? please help.

Naresh said:   1 decade ago
If we add the work of b and c for 1 day we get 1/30 + 1/60=1/20.

First day = 1/20.

Second day =2/20.

Third day =4/20 // work of b & c is added 3/20 + 1/20.

Every 3 days 4/20.

For 6 days we get 8/20.

For 9 days we get 12/20.

For 12 days we get 16/20.

For 15 days we get 20/20 = 1. Job over.

Nitin.killekar@gmail.com said:   1 decade ago
In the last step the multiplication of 3 and 5 is for the no.of persons (3) and amount of work done (5).

Madhuri Choudhary said:   1 decade ago
I didn't understood how did they calculated the work done in 3 days. Can somebody explain me clearly?

Asanka said:   1 decade ago
If x = A worked day

{x*1/20 + x/3*(1/30+1/20)} = 1

x/20+x/60 = 1

x = 15.

Saf said:   1 decade ago
There is confusion because the number is same for A working for 2 days (i.e.1/10 Days) and all three, A+B+C=1/10 days.

Hence its.

=2 working days of A 1/10+ All 3 together 1/10 days.

i.e. (1/10+1/10).

Krats said:   1 decade ago
1/5 works is being done in 3 days.

i.e 1 of the 5 parts of work is done in 3 days.

So total there are 5 parts of work which will take 5*3=15 days.

No one said:   1 decade ago
A's one day work is 1/20 ,

Therefore A's 2 day work will be (1/20)*2=(1/10),

Now (A+B+C)'s one day work will be = (1/20)+(1/30)+(1/60)=(1/10).

Since A is assisted on every third day of his work then total work done in three days will include A's 2 day's of work plus the work done on third day, that is (A+B+C)'s one day work,

Therefore work done in 3 days will be,A's two days work (1/10 )+ A,B,C's one day work (1/10)= (1/5).

Now in three days 1 out of 5 parts of work is done , and yet 4 parts are to be done there fore 4*3= 12 days and since we have calculated the earlier 1 parts requirement of days i,e 3 days total days will to finish 5 parts will be (12+3)= 15 days.

SHAZAM said:   1 decade ago
Here's a simple explanation :

WORK = (Rate)*(Time) ***time will cancel out***

First Day: Person A does all the work.

His working rate is 1/20 so (1/20)*1day = 1/20 work.

Second Day: Person A does all the work.

His working rate is 1/20 so (1/20)*1day = 1/20 work.

All in all in 2 days is 2/20 or 1/10.

Third Day: Person A is assisted by B and C.

(1/20)+(1/30)+(1/60) times 1 day = 1/10.

All in all in 3 days is (1/10)+(1/10)= 1/5 work is done.

So 4/5 remaining..

Question Says B and C assisted A EVERY third day.

Repeat the process until you get 5/5 or 1 full work that would be on the 15th day, A will complete 5/5 or 1 full work.

Divya said:   1 decade ago
Why we taken 1/10+1/10?


Post your comments here: