Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 11 of 36.
SHAZAM said:
1 decade ago
Here's a simple explanation :
WORK = (Rate)*(Time) ***time will cancel out***
First Day: Person A does all the work.
His working rate is 1/20 so (1/20)*1day = 1/20 work.
Second Day: Person A does all the work.
His working rate is 1/20 so (1/20)*1day = 1/20 work.
All in all in 2 days is 2/20 or 1/10.
Third Day: Person A is assisted by B and C.
(1/20)+(1/30)+(1/60) times 1 day = 1/10.
All in all in 3 days is (1/10)+(1/10)= 1/5 work is done.
So 4/5 remaining..
Question Says B and C assisted A EVERY third day.
Repeat the process until you get 5/5 or 1 full work that would be on the 15th day, A will complete 5/5 or 1 full work.
WORK = (Rate)*(Time) ***time will cancel out***
First Day: Person A does all the work.
His working rate is 1/20 so (1/20)*1day = 1/20 work.
Second Day: Person A does all the work.
His working rate is 1/20 so (1/20)*1day = 1/20 work.
All in all in 2 days is 2/20 or 1/10.
Third Day: Person A is assisted by B and C.
(1/20)+(1/30)+(1/60) times 1 day = 1/10.
All in all in 3 days is (1/10)+(1/10)= 1/5 work is done.
So 4/5 remaining..
Question Says B and C assisted A EVERY third day.
Repeat the process until you get 5/5 or 1 full work that would be on the 15th day, A will complete 5/5 or 1 full work.
Divya said:
1 decade ago
Why we taken 1/10+1/10?
Suresh Kumar said:
1 decade ago
@Divya.
First Two days work done by A = (1/20)+(1/20)=> 2/20=> 1/10.
Third day work done by A,B,C = (1/20)+(1/30)+(1/60)=> 6/60 => 1/10.
Total work Done in 3 days= (1/10)+(1/10)=2/10 =>1/5.
First Two days work done by A = (1/20)+(1/20)=> 2/20=> 1/10.
Third day work done by A,B,C = (1/20)+(1/30)+(1/60)=> 6/60 => 1/10.
Total work Done in 3 days= (1/10)+(1/10)=2/10 =>1/5.
Anurag said:
1 decade ago
Let N be the total no.of days A has to work. So, a/q B and C works only for N/3 days. Total work = 1.
Therefore,
N*(1/20)+ (N/3)*((1/30)+(1/60)) = 1.
Solving this , you will get N = 15.
Therefore,
N*(1/20)+ (N/3)*((1/30)+(1/60)) = 1.
Solving this , you will get N = 15.
Seema duhan said:
1 decade ago
First Two days work done by A = (1/20)+(1/20)=> 2/20=> 1/10.
Third day work done by A, B, C = (1/20)+(1/30)+(1/60)=> 6/60 => 1/10.
3 days work done: 1/5.
Then 1 day work done: (1/5)*(1/3) = 1/15.
So the answer is 115 days.
Third day work done by A, B, C = (1/20)+(1/30)+(1/60)=> 6/60 => 1/10.
3 days work done: 1/5.
Then 1 day work done: (1/5)*(1/3) = 1/15.
So the answer is 115 days.
V.MADANKUMAR said:
1 decade ago
A's 2 day's work = (1/20x2) = 1/10.
(A + B + C)'s 1 day's work = [(1/20)+(1/30)+(1/60)] = 6/60 = 1/10.
Work done in 3 days = [(1/10)+(1/10)] = 1/5.
Now what they ask "How many days can "A" do the work?"
Here revise the FORMULA NO:2.
That is:
Days from Work:
If A's 1 day's work =1/n,then A can finish the work in n days.
Here ===> [1 DAY's work = NO.of WORK / required "n" Day's do the work ].
We want no.of DAY's;
So rearrange the formula; we get,
No.of WORK = (1DAY's work * "n" DAY's) ------> take eqn no.1.
Now, (1/5) work is done in 3 days.
3 = 1/5.
So apply above the data's in eqn no.1.
1(No.of Work) = (Day's of Work )3 * ("n" DAY's)5.
1(No.of Work) = 15 Day's
So "A" is require 15 Day's to do a 1 work.
"I HOPE U WILL B UNDERSTAND"
(A + B + C)'s 1 day's work = [(1/20)+(1/30)+(1/60)] = 6/60 = 1/10.
Work done in 3 days = [(1/10)+(1/10)] = 1/5.
Now what they ask "How many days can "A" do the work?"
Here revise the FORMULA NO:2.
That is:
Days from Work:
If A's 1 day's work =1/n,then A can finish the work in n days.
Here ===> [1 DAY's work = NO.of WORK / required "n" Day's do the work ].
We want no.of DAY's;
So rearrange the formula; we get,
No.of WORK = (1DAY's work * "n" DAY's) ------> take eqn no.1.
Now, (1/5) work is done in 3 days.
3 = 1/5.
So apply above the data's in eqn no.1.
1(No.of Work) = (Day's of Work )3 * ("n" DAY's)5.
1(No.of Work) = 15 Day's
So "A" is require 15 Day's to do a 1 work.
"I HOPE U WILL B UNDERSTAND"
(3)
Sundas said:
1 decade ago
I didn't get step 1 how a 2 days work? I mean why we multiply with 2?
Ganesh said:
1 decade ago
Guys, as per my understanding,
1st day A complete 1/20th of work.
2nd day A completes 2/20th of work.
3rd day A along with B and C completes (3/20+1/30+1/60) i.e., 1/5th of the work.
Could some one explain how to calculate?
4th day of A's work ?
5th day of A's work?
6th day of A along with B and C ?
1st day A complete 1/20th of work.
2nd day A completes 2/20th of work.
3rd day A along with B and C completes (3/20+1/30+1/60) i.e., 1/5th of the work.
Could some one explain how to calculate?
4th day of A's work ?
5th day of A's work?
6th day of A along with B and C ?
Arijit Roy said:
1 decade ago
It would be better if it is done in this way.
B, C assist A on the 3rd day so directly we get,
3/20(3 day's of A) + 1/30(assistance of B) + 1/60(assistance of C) = 1/5.
So 1/5 done in 3 days whole is done in 15 days.
B, C assist A on the 3rd day so directly we get,
3/20(3 day's of A) + 1/30(assistance of B) + 1/60(assistance of C) = 1/5.
So 1/5 done in 3 days whole is done in 15 days.
Bond said:
1 decade ago
1/5 of work --->3 days.
1 complete work ---> ?
= (1*3)/(1/5).
= 15 days.
1 complete work ---> ?
= (1*3)/(1/5).
= 15 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers