Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
Discussion:
357 comments Page 10 of 36.
Trisha said:
1 decade ago
Whole work will be done in (3 x 5) = 15 days.
I m unable to understand a last step. Explain me?
How they multiply by 5?
I m unable to understand a last step. Explain me?
How they multiply by 5?
Durga said:
1 decade ago
LCM of 20,30,60 is 600
A's work is 600/20
if b and c on third day then 2 days(first and second) for A and 1 day for B and c(third day)
so A's work is 600/(20*2)=600/40=15
A's work is 600/20
if b and c on third day then 2 days(first and second) for A and 1 day for B and c(third day)
so A's work is 600/(20*2)=600/40=15
Priti said:
1 decade ago
We have already calculate 1/5 for 3 days. Then why again multiplying by 3? please help.
Naresh said:
1 decade ago
If we add the work of b and c for 1 day we get 1/30 + 1/60=1/20.
First day = 1/20.
Second day =2/20.
Third day =4/20 // work of b & c is added 3/20 + 1/20.
Every 3 days 4/20.
For 6 days we get 8/20.
For 9 days we get 12/20.
For 12 days we get 16/20.
For 15 days we get 20/20 = 1. Job over.
First day = 1/20.
Second day =2/20.
Third day =4/20 // work of b & c is added 3/20 + 1/20.
Every 3 days 4/20.
For 6 days we get 8/20.
For 9 days we get 12/20.
For 12 days we get 16/20.
For 15 days we get 20/20 = 1. Job over.
Nitin.killekar@gmail.com said:
1 decade ago
In the last step the multiplication of 3 and 5 is for the no.of persons (3) and amount of work done (5).
Madhuri Choudhary said:
1 decade ago
I didn't understood how did they calculated the work done in 3 days. Can somebody explain me clearly?
Asanka said:
1 decade ago
If x = A worked day
{x*1/20 + x/3*(1/30+1/20)} = 1
x/20+x/60 = 1
x = 15.
{x*1/20 + x/3*(1/30+1/20)} = 1
x/20+x/60 = 1
x = 15.
Saf said:
1 decade ago
There is confusion because the number is same for A working for 2 days (i.e.1/10 Days) and all three, A+B+C=1/10 days.
Hence its.
=2 working days of A 1/10+ All 3 together 1/10 days.
i.e. (1/10+1/10).
Hence its.
=2 working days of A 1/10+ All 3 together 1/10 days.
i.e. (1/10+1/10).
Krats said:
1 decade ago
1/5 works is being done in 3 days.
i.e 1 of the 5 parts of work is done in 3 days.
So total there are 5 parts of work which will take 5*3=15 days.
i.e 1 of the 5 parts of work is done in 3 days.
So total there are 5 parts of work which will take 5*3=15 days.
No one said:
1 decade ago
A's one day work is 1/20 ,
Therefore A's 2 day work will be (1/20)*2=(1/10),
Now (A+B+C)'s one day work will be = (1/20)+(1/30)+(1/60)=(1/10).
Since A is assisted on every third day of his work then total work done in three days will include A's 2 day's of work plus the work done on third day, that is (A+B+C)'s one day work,
Therefore work done in 3 days will be,A's two days work (1/10 )+ A,B,C's one day work (1/10)= (1/5).
Now in three days 1 out of 5 parts of work is done , and yet 4 parts are to be done there fore 4*3= 12 days and since we have calculated the earlier 1 parts requirement of days i,e 3 days total days will to finish 5 parts will be (12+3)= 15 days.
Therefore A's 2 day work will be (1/20)*2=(1/10),
Now (A+B+C)'s one day work will be = (1/20)+(1/30)+(1/60)=(1/10).
Since A is assisted on every third day of his work then total work done in three days will include A's 2 day's of work plus the work done on third day, that is (A+B+C)'s one day work,
Therefore work done in 3 days will be,A's two days work (1/10 )+ A,B,C's one day work (1/10)= (1/5).
Now in three days 1 out of 5 parts of work is done , and yet 4 parts are to be done there fore 4*3= 12 days and since we have calculated the earlier 1 parts requirement of days i,e 3 days total days will to finish 5 parts will be (12+3)= 15 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers