30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
30 days
40 days
60 days
70 days
Answer: Option
Explanation:

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30

Solving these two equations, we get: x = 1 and y = 1
60 60

B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Discussion:
97 comments Page 9 of 10.

Pandit said:   1 decade ago
@Kanna.

You explain very easly. Thanks a lot.

Student said:   1 decade ago
How can we write 16x+44y=1. I cant understand.
(1)

Shyam said:   1 decade ago
I got the same answer as Sai and Kaustubha.

Jitender said:   10 years ago
I want any short method of this question.

Bisu said:   9 years ago
Can somebody solve it in the shortcut?

Kaavya said:   7 years ago
Thanks for the answer @Tapash Dey.

Bangaram said:   1 decade ago
Kanna your explaination was good.

Santh said:   1 decade ago
Selvi. You are wrong absolutely.
(1)

Soniya said:   1 decade ago
@kanna.

You are right. Thanks.

Yogi said:   1 decade ago
@Manasa

Yes you are corrrect.


Post your comments here:

Your comments will be displayed after verification.