Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 30)
30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
30 days
40 days
60 days
70 days
Answer: Option
Explanation:

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30

Solving these two equations, we get: x = 1 and y = 1
60 60

B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Discussion:
97 comments Page 6 of 10.

Ray said:   10 years ago
I have figure out the easiest way to understand the equation:

Let's say the speed of work done by each A and B in one day:

A+B = 1/30 (that's mean only (1/30)*100 = 3.33% whole work done).

In order to complete the whole task is 100%.

So, 16A+44B = (100/100) = 1.

This explained why the number 1 exist in the equation. The other part can be solved on your own.

Pikot said:   9 years ago
Is there a formula?

SRI said:   9 years ago
1/30 - 1/16 = 7/240

2*1 / 44 = 1/22

7/240 - 1/22 = 43/2640

Vinayan said:   9 years ago
Total work is equal to the LCM of 30, 16 & 44. ie 2640.

B finished the work in 2640/ 44 = 60 days.

Mona said:   9 years ago
How we are getting 1 in the equation 16x+44y please Explain.

Jyoti Singh said:   9 years ago
Can anyone tell how to solve efficiency questions of time & work?

Like.

A is 140% efficient than B. B starts the work & does 5 days then A completes the remaining work in 10 days. In how many days does A take to complete the same work.

Please, anyone tell me.

Dhanesh ck said:   9 years ago
I will tell the simplest way. From this question, it's clear that A worked for 16 days and B worked for 44 days so 1/30 * 16 + 1/B * 28 = 1. So we get B = 60.

Dhakshina said:   9 years ago
Given X + Y =30.

They never mentioned any efficiency (like B is twice as good).

Assume that they are equal efficiency.

So A Did only 16 days work and B completed remaining work in 44 days.

Therefore total work of B is 44 + 16 = 60.

Total work of A is also 60.

Bisu said:   9 years ago
Can somebody solve it in the shortcut?

Aakash said:   9 years ago
2 workers A + B together could finish a work in 8 days they work together for 6 days & A left the works the remaining works was completed by B alone in 6 days. How many days would each take to complete the individual?

How to solve this problem?


Post your comments here:

Your comments will be displayed after verification.