Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 30)
30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
30 days
40 days
60 days
70 days
Answer: Option
Explanation:

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30

Solving these two equations, we get: x = 1 and y = 1
60 60

B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Discussion:
97 comments Page 3 of 10.

NIshil said:   6 years ago
a+b = can do a work in 30 days.
A work for 16 day means 14 days work left.
B do the work for 44 days means extra 14-day work from 30-day timeline.

That is 14. a = 14.b (14day work left is don by b in extra 14-day work).
a/b = 1/1.
Total work = 30.(1+1)= 60 ( 30 days and both efficiency).
B alone can do= total work/b efficiency= 60/1.
60 is the answer.
(1)

Hetal said:   1 decade ago
Yes I also get the same answer like @Sai and @Kaustubha Sen.

a+b = 1/30 (1 day's work).

So (a+b) work together for 16 days.

So, 1/30*16 = 16/30. So we get 8/15 work done together for 16 days.

Now remaining work = 1-8/15 we get 7/15.

That's why if 7/15 remaining work b takes 44 days then work done by b in 1 day.

= 1*7/44*15.

I got 94.28.

IOvd said:   1 decade ago
@Sneha.

x+y = 1/30 .....(i).
16x+44y = 1 .....(ii).

Multiply equation (i) by 16 we get,

16x+16y = 8/15(ie 16/30).....(iii).

Now subtract equation (iii) from equation (ii).

16x+44y = 1.
- 16x+16y = 8/15.
-----------------
+28y = 7/15 (ie 1-8/15).

Now y = 7/15*1/28.
y = 1/15*1/4.
y = 1/60.

I hope u get it now.

Subhant said:   8 years ago
Solving the equations is tiresome brothers.
Instead take like

16a +44 b = 30 a + 30b.
a/b = 1/1
So if a one day work is 1 and b one day work is one and when they work together they do 2 units of work every day.

this means there is 30x2 = 60 units of work.

B can do it in = (total unit of work)/(B's one day work) = 60 days.

Sameer said:   5 years ago
A's 1 day work = x.
B's 1 day work = y.

They work together x+y= 1/30; x = 1/30-y.
A having work for 16 days and B finishes remaining work alone 44 days 16x+44y = 1.

16*(1/30-y)+ 44y =1.
16/30-16y + 44y =1.
16/30 -28y =1.
28y= 1-16/30.
28y=7/15.
y=7/15*28.
y=1/60.

B's alone do the work in = 1/60 days = 60days.

Harish said:   1 decade ago
I don't think we should bother about 30 days' combined work. That piece of problem is, I think, meant to confuse us. Because he wishes to know B's individual capacity of doing what is left out by A's individual work.

Whatever A leaves behind, B finishes it.

Hence it is as simple as 16+44 = 60 days.

Sai said:   1 decade ago
If 8/15 of the work is done by A in 16 days, then remaining 7/15 of the work is done by B in 44 days right....then why not cross multiply for 15/15 of the work.

I am getting a wrong answer doing this. Can anyone explain please.

7/15 work ----- 44 days.
15/15 work ----- k days.

k = 44*15/7 = 94.28.

Sagar parida said:   8 years ago
Please, anyone help me out from this question--.

A and B can do a work together in 10 days, B and C can do the same work in 18 days, if A starts the work and after working 5 days B do the work for 15 days and remaining work in done by C than find in how many days will C complete the work alone?

Manasa said:   1 decade ago
A's 1 day work ,consider X
B's 1 day work ,consider Y
(A+B) 1 day work=(X+Y)=1/30
next condition:
A works for 16 days=16*X
B works for 44 days for remaining work to complete=44*Y
to complete whole work;16X+44Y=1
by solving both equations ,we get
X=1/60,Y=1/60
B can complete work in 60 days.

Avi said:   1 decade ago
For completion of one work it took A, B for 30 days.

So let A's one day work is x & B's one day work is y.

From above we can write 1 work=30x+30y.

But in second case a worked for 16 days & B worked for 44days.

Therefore,

16x+44y=1 work.

By solving we can get y=1/60 work.


Post your comments here:

Your comments will be displayed after verification.