Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
6 days
10 days
15 days
20 days
Answer: Option
Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5

Remaining work = 1 - 1 = 4 .
5 5

(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15

Now, 2 work is done by X and Y in 1 day.
15

So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

Discussion:
68 comments Page 3 of 7.

Ramchandra said:   2 decades ago
Hai frnds this is very long process....
I can find one short cut ..i.e
Suppose x & Y do the work = k days (assume)
y do work = k-1 days
we now that
(x/20)+((x-4)/12))=1 ( By solving )
x=10 days...

Ims said:   7 years ago
X=20,Y=12.
SO LCM=60
X=3 unit /day.
Y=5 unit /day.
According to the question;

x work for 4 days alone so 3 *4 = 12.
So 60-12=48.
X+y=8 units.
Therefore, 48÷8=6.
So, 6+4(days of A alone works) = 10.
(4)

ANURAG said:   1 decade ago
(x and y)'s one day work= 2/15
Therefore total number of days for the total work= 15/2
And,total number of days for 4/5 of the work=( 15/2 )*(4/5)
Hence total time = 6+4 = 10 days

Prienka said:   7 years ago
Why we are calculating total time taken i.e 6+4 days. The question was asked how long did the work last?

Should it be 6 days only right? Anybody can clear my confusion?

Inna Reddy Chilakala said:   10 years ago
Total work = X.

A = X (begin the work and he is in End of the work).

B = X-4 (After 4 days he joined).

= X/20 + X - 4/12 = 1.

= 3X + 5X - 20/60.

8X = 80.

X = 10.

Padma said:   1 decade ago
A+B can work
1/20+1/12=8/60.

A can work =4*1/20=1/5.

Remaining work=1-1/5=4/5.

A+B work to days 1/n formula=60/8.

60/8*4/5=6 days.

Total day taken will be=6+4=10.

Neeru said:   2 decades ago
Always total work will be considered as 1, in dat 1/5 th work is already done and the remaining work is 1-1/5 =4/5 dats it.

I hope you understand this.

Amarnath said:   1 decade ago
Sorry @Zia Don't apply formulas it loses confidence for others. Whatever they know will apply if try tell in simple answer don't tell with formulas.

Zia said:   1 decade ago
Hi, I have a shortcut.

(X-a)*Y/X+Y [X=20,Y=12,a=4]

= (20-4)*12/20+12.

= 16*12/32.

= 12/2.

= 6.

So, total time taken (6+4) = 10 days.

Kavya said:   1 decade ago
Short cut: A=20, B=12.

4 days left: 20-4 = 16.

B joined : (1/20) + (1/12) = 15/2.

Therefore: (16/20)(15/2) = 6.

Total days = 6+4 = 10.
(1)


Post your comments here:

Your comments will be displayed after verification.