Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Answer: Option
Explanation:
| Work done by X in 4 days = | ![]() |
1 | x 4 | ![]() |
= | 1 | . |
| 20 | 5 |
| Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 4 | . |
| 5 | 5 |
| (X + Y)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 8 | = | 2 | . |
| 20 | 12 | 60 | 15 |
| Now, | 2 | work is done by X and Y in 1 day. |
| 15 |
| So, | 4 | work will be done by X and Y in | ![]() |
15 | x | 4 | ![]() |
= 6 days. |
| 5 | 2 | 5 |
Hence, total time taken = (6 + 4) days = 10 days.
Discussion:
69 comments Page 3 of 7.
Patel Komal said:
1 decade ago
Please help me to get this, why you take (1/20 * 4)?
Sachin said:
1 decade ago
Please help me to understand this, why we took 15/2 instead of 2/15?
Thank in advance.
Thank in advance.
Inna Reddy Chilakala said:
1 decade ago
Total work = X.
A = X (begin the work and he is in End of the work).
B = X-4 (After 4 days he joined).
= X/20 + X - 4/12 = 1.
= 3X + 5X - 20/60.
8X = 80.
X = 10.
A = X (begin the work and he is in End of the work).
B = X-4 (After 4 days he joined).
= X/20 + X - 4/12 = 1.
= 3X + 5X - 20/60.
8X = 80.
X = 10.
Suraj said:
1 decade ago
They said in question in a piece of so how it's possible whole work done by them.
Sonu jangra said:
1 decade ago
x can do a work in 20 days.
y can do a work in 12 days.
To find total work, take LCM of 20 and 12 i.e. 60.
So x+y total 1 day's work = (1/20+1/1/12) = 2/15.
But x work alone = 1/4 day's. Remain work = (1-1/4) = 3/4.
Now, work will be done by x and y = 2/15*3/4 = 1/10.
So 10 day's.
y can do a work in 12 days.
To find total work, take LCM of 20 and 12 i.e. 60.
So x+y total 1 day's work = (1/20+1/1/12) = 2/15.
But x work alone = 1/4 day's. Remain work = (1-1/4) = 3/4.
Now, work will be done by x and y = 2/15*3/4 = 1/10.
So 10 day's.
Ajay said:
9 years ago
x+4/20+x/12 = 1.
3(x+4)+5(x)/60 = 1.
3x+12+5x = 60.
8x+12 = 60.
8x = 60-12.
8x = 48.
x = 6.
i.e., x+4 = 6+4.
10 days.
3(x+4)+5(x)/60 = 1.
3x+12+5x = 60.
8x+12 = 60.
8x = 60-12.
8x = 48.
x = 6.
i.e., x+4 = 6+4.
10 days.
Prudhvi said:
9 years ago
(4/20)+x(1/20+1/12) = 1,
Solve for x.
x=6.
Total days = x+4.
Solve for x.
x=6.
Total days = x+4.
Bhavesh said:
9 years ago
Can we do like this?
(4/20)+(x/12)=1.
It give 9.6 and dats means 10days.
(4/20)+(x/12)=1.
It give 9.6 and dats means 10days.
Mr. MP said:
9 years ago
X"s one day work is 1/20.
so he worked 4 days alone which is,
4* 1/20 = 1/5 remember the Confusion avoider formula below,
(Days * single day"s work( together or alone, this case alone by X) = completed work) remember this
when we know days RHS is Completed work, if Days not known RHS is Pending work
1/5 work is completed out entire work 1
entire work - completed work = 1-1/5 = 4/5 or 80% which is pending work
pending work is 4/5 which is done by X and Y
one day's work of X and Y is 1/20 + 1/12 = 2/15 this is 1 day"s work and Inverse is the Days. If you ask WHY see X 1/20 is one day's work of X, inverse which is 20 is the number of days. Is it clear?
15/2 * 4/5= 6 days
Use this formula.
Days * single day's work ( this case by X and Y) = remaining or completed work.
Days we have to find * 2/15 = 4/5 which gives 4/5* 15/2 =6.
Now 6 days for 80% or 4/5 of the job by x and Y and 4 days for initial 1/5 or 20% of the job by x.
So, total 10 days.
so he worked 4 days alone which is,
4* 1/20 = 1/5 remember the Confusion avoider formula below,
(Days * single day"s work( together or alone, this case alone by X) = completed work) remember this
when we know days RHS is Completed work, if Days not known RHS is Pending work
1/5 work is completed out entire work 1
entire work - completed work = 1-1/5 = 4/5 or 80% which is pending work
pending work is 4/5 which is done by X and Y
one day's work of X and Y is 1/20 + 1/12 = 2/15 this is 1 day"s work and Inverse is the Days. If you ask WHY see X 1/20 is one day's work of X, inverse which is 20 is the number of days. Is it clear?
15/2 * 4/5= 6 days
Use this formula.
Days * single day's work ( this case by X and Y) = remaining or completed work.
Days we have to find * 2/15 = 4/5 which gives 4/5* 15/2 =6.
Now 6 days for 80% or 4/5 of the job by x and Y and 4 days for initial 1/5 or 20% of the job by x.
So, total 10 days.
Ved Prakash Singh said:
9 years ago
4/20+x/20+x/12=1.
X=6 so total days=6+4=10days.
X=6 so total days=6+4=10days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers

