Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Answer: Option
Explanation:
Work done by X in 4 days = | ![]() |
1 | x 4 | ![]() |
= | 1 | . |
20 | 5 |
Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 4 | . |
5 | 5 |
(X + Y)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 8 | = | 2 | . |
20 | 12 | 60 | 15 |
Now, | 2 | work is done by X and Y in 1 day. |
15 |
So, | 4 | work will be done by X and Y in | ![]() |
15 | x | 4 | ![]() |
= 6 days. |
5 | 2 | 5 |
Hence, total time taken = (6 + 4) days = 10 days.
Discussion:
68 comments Page 4 of 7.
Bhavesh said:
8 years ago
Can we do like this?
(4/20)+(x/12)=1.
It give 9.6 and dats means 10days.
(4/20)+(x/12)=1.
It give 9.6 and dats means 10days.
Mr. MP said:
8 years ago
X"s one day work is 1/20.
so he worked 4 days alone which is,
4* 1/20 = 1/5 remember the Confusion avoider formula below,
(Days * single day"s work( together or alone, this case alone by X) = completed work) remember this
when we know days RHS is Completed work, if Days not known RHS is Pending work
1/5 work is completed out entire work 1
entire work - completed work = 1-1/5 = 4/5 or 80% which is pending work
pending work is 4/5 which is done by X and Y
one day's work of X and Y is 1/20 + 1/12 = 2/15 this is 1 day"s work and Inverse is the Days. If you ask WHY see X 1/20 is one day's work of X, inverse which is 20 is the number of days. Is it clear?
15/2 * 4/5= 6 days
Use this formula.
Days * single day's work ( this case by X and Y) = remaining or completed work.
Days we have to find * 2/15 = 4/5 which gives 4/5* 15/2 =6.
Now 6 days for 80% or 4/5 of the job by x and Y and 4 days for initial 1/5 or 20% of the job by x.
So, total 10 days.
so he worked 4 days alone which is,
4* 1/20 = 1/5 remember the Confusion avoider formula below,
(Days * single day"s work( together or alone, this case alone by X) = completed work) remember this
when we know days RHS is Completed work, if Days not known RHS is Pending work
1/5 work is completed out entire work 1
entire work - completed work = 1-1/5 = 4/5 or 80% which is pending work
pending work is 4/5 which is done by X and Y
one day's work of X and Y is 1/20 + 1/12 = 2/15 this is 1 day"s work and Inverse is the Days. If you ask WHY see X 1/20 is one day's work of X, inverse which is 20 is the number of days. Is it clear?
15/2 * 4/5= 6 days
Use this formula.
Days * single day's work ( this case by X and Y) = remaining or completed work.
Days we have to find * 2/15 = 4/5 which gives 4/5* 15/2 =6.
Now 6 days for 80% or 4/5 of the job by x and Y and 4 days for initial 1/5 or 20% of the job by x.
So, total 10 days.
Ved Prakash Singh said:
8 years ago
4/20+x/20+x/12=1.
X=6 so total days=6+4=10days.
X=6 so total days=6+4=10days.
Shree said:
8 years ago
Clear and detailed explanation. Thank you.
Prienka said:
7 years ago
Why we are calculating total time taken i.e 6+4 days. The question was asked how long did the work last?
Should it be 6 days only right? Anybody can clear my confusion?
Should it be 6 days only right? Anybody can clear my confusion?
Jjjjjjjjjj said:
1 decade ago
Please explain clealrly.
Santosh said:
1 decade ago
Well a simple logic
1day work x =1/20
y=1/12
x first start and works upto 4 days=4*1/20
then both x and y works upto some day to completework=a(1/20+1/12)
add (4*1/20)+a(1/20+1/12)=1
we will get the days where both x and y worked=a=6
So total days to complete work =4+6=10.
1day work x =1/20
y=1/12
x first start and works upto 4 days=4*1/20
then both x and y works upto some day to completework=a(1/20+1/12)
add (4*1/20)+a(1/20+1/12)=1
we will get the days where both x and y worked=a=6
So total days to complete work =4+6=10.
Sree said:
1 decade ago
How 6+4?y should we add. Please help.
Sahib said:
1 decade ago
Take it this way
1/5 work x does in 4 days
Remaining 4/5 is to be found
X+y does 1/20+1/12 in 1 day
Therefore x+y=2/15 w/d
Therefore 4/5 w = 2/15(w/d)/4/5(w)
We get 1/6(1/d)
Therefore 6 days
Therefore total wrk in 10 days
1/5 work x does in 4 days
Remaining 4/5 is to be found
X+y does 1/20+1/12 in 1 day
Therefore x+y=2/15 w/d
Therefore 4/5 w = 2/15(w/d)/4/5(w)
We get 1/6(1/d)
Therefore 6 days
Therefore total wrk in 10 days
Anwesh said:
1 decade ago
Harsha realy well done.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers