Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 16)
16.
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
6 days
10 days
15 days
20 days
Answer: Option
Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5

Remaining work = 1 - 1 = 4 .
5 5

(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15

Now, 2 work is done by X and Y in 1 day.
15

So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

Discussion:
68 comments Page 2 of 7.

Gowtham said:   4 months ago
One days work of X=1/20.
One days work of Y=1/12.
Four days work is. 4[1/X = 1/20],
=> 4/X = 4/20,
=>4/X. = 1/5
1 is the whole work.
1-1/5 = 4/5.
Then 4/5 work is to be done.

X's and Y's one day work is = 1/20+1/12=2/15.

Let "K" be the number of days taken by X and Y to complete the work.

1 day --->2/15.
K days --->4/5.
4/5 ×1 = K× 2/15.
4/5 ×15/2 = K.
K = 2×3 = 6 days.
4 days work of X.
6 days work of X and Y.

4 + 6 =10 days.
(1)

Shehina.s.p said:   2 decades ago
Please explain how {15/2*4/5} comes?
(1)

Chandu said:   10 years ago
X 1 days work = 1/20.

Y 1 days work = 1/12.

X work for 4 days ---> 4/20 = 1/5.

Remaining work to be done--->1-1/5 = 4/5.

After 4 days Y is join with X to work.

So X+Y 1 day's work = (1/20+1/12) = 2/15 ---> X+Y finish work in 15/2 days.

So X+Y finish 4/5 part of work in 15/2*4/5 ----> 6 days.

Total days ---> 4+6 = 10 days.
(1)

Shanmugam said:   9 years ago
(1-1/5) = 4/5? Please explain it.
(1)

Kavya said:   1 decade ago
Short cut: A=20, B=12.

4 days left: 20-4 = 16.

B joined : (1/20) + (1/12) = 15/2.

Therefore: (16/20)(15/2) = 6.

Total days = 6+4 = 10.
(1)

Nishesh kumar singh said:   4 years ago
@All.

4/5 is the remaining work which is divided by 2/15 which is 1-day work by x and y to find the no. Of days i.e.4/5/2/15.
(1)

Akil Prakash said:   7 years ago
Thank you @Inna Reddy Chilakala.

Akhil said:   1 decade ago
Can anyone explain this problem clearly.

Sonu jangra said:   10 years ago
x can do a work in 20 days.

y can do a work in 12 days.

To find total work, take LCM of 20 and 12 i.e. 60.

So x+y total 1 day's work = (1/20+1/1/12) = 2/15.

But x work alone = 1/4 day's. Remain work = (1-1/4) = 3/4.

Now, work will be done by x and y = 2/15*3/4 = 1/10.

So 10 day's.

Suraj said:   10 years ago
They said in question in a piece of so how it's possible whole work done by them.


Post your comments here:

Your comments will be displayed after verification.