Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Answer: Option
Explanation:
Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.
Suppose Tanya takes x days to do the work.
5 : 4 :: 20 : x ![]() |
![]() |
4 x 20 | ![]() |
5 |
x = 16 days.
Hence, Tanya takes 16 days to complete the work.
Discussion:
94 comments Page 9 of 10.
Kundan said:
1 decade ago
Tanya does 25% efficient work. What does this mean? This means that the work that Sakshi completes is 100% and Tanya does the same work but 125%. So see efficiency as the greater percentage of work being done by Tanya 125% is greater than 100%.
For example if a does 20 units of work in 5 hrs and b does 40 units of work in 5 hrs. Then 1 hr work of A and B is 4 and 8 respectively. What does this mean? It means that B is doing more work in same no of hrs.
Now consider it as B was doing 40 units of work in 5 hrs. So what is his time for 1 unit of work? its 5/40. i.e 1/8! and similarly for A it is 1/4. So in respect of timing who is fast or efficient? Its certainly B because 1/8 is smaller than 1/4!
For example if a does 20 units of work in 5 hrs and b does 40 units of work in 5 hrs. Then 1 hr work of A and B is 4 and 8 respectively. What does this mean? It means that B is doing more work in same no of hrs.
Now consider it as B was doing 40 units of work in 5 hrs. So what is his time for 1 unit of work? its 5/40. i.e 1/8! and similarly for A it is 1/4. So in respect of timing who is fast or efficient? Its certainly B because 1/8 is smaller than 1/4!
Jai said:
1 decade ago
Hey, how come it is 16?
If Tanya takes 16 days to complete, then it means Sakshi is 25% slower than Tanya. But we have calculate Tanya's time who is 25% faster than Sakshi.
So I reckon it should be 15. Please correct me if I am wrong.
If Tanya takes 16 days to complete, then it means Sakshi is 25% slower than Tanya. But we have calculate Tanya's time who is 25% faster than Sakshi.
So I reckon it should be 15. Please correct me if I am wrong.
Deepa said:
1 decade ago
20-25%[20] = 15 days.
Pankaj said:
10 years ago
Answer will be 25.
If the ratio taken is T:S::T:S.
125:100::X:20.
5:4::X:20 = 25.
x is no. of days taken by Tanya complete a work.
If the ratio taken is T:S::T:S.
125:100::X:20.
5:4::X:20 = 25.
x is no. of days taken by Tanya complete a work.
Jasmin said:
1 decade ago
Can you explain me chain rule please?
5:4 :: 20:x.
5:4 :: 20:x.
Geetha said:
1 decade ago
Give a brief explain how 125:100 come?
Anshu said:
1 decade ago
Hey,
You can understand it like this.
As we know working efficiency of sakshi is 1/20.
And working efficiency of tanya is 25% greater.
So tanya eff = 1/20*(125/100)=1/16.
Hence time 16 days.
You can understand it like this.
As we know working efficiency of sakshi is 1/20.
And working efficiency of tanya is 25% greater.
So tanya eff = 1/20*(125/100)=1/16.
Hence time 16 days.
Pavan said:
1 decade ago
Here question starts with sakshi so we must take s=100.
Then 25% eff so T=75.
Then the ratio we get is 3:4.
Answer will be 15.
How can it be 16.
Can anyone please?
Then 25% eff so T=75.
Then the ratio we get is 3:4.
Answer will be 15.
How can it be 16.
Can anyone please?
Manjula said:
1 decade ago
Sakshi working days in 20 days means 100%.
Tanya working days ?
100%-75% = 25%
So 20*25/125 = 4.
20 days - 4 = 16 days.
Tanya working days ?
100%-75% = 25%
So 20*25/125 = 4.
20 days - 4 = 16 days.
Ramesh said:
1 decade ago
Sakshi's one day work is 1/20.
Tanya is 25% of sakshi it means 1/20+25%1/20.
= (1/20+25/100*1/20).
= (1/20+1/80).
= 1/16 for one day.
So 16 days to do total work.
Tanya is 25% of sakshi it means 1/20+25%1/20.
= (1/20+25/100*1/20).
= (1/20+1/80).
= 1/16 for one day.
So 16 days to do total work.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers