Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 20)
20.
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
15
16
18
25
Answer: Option
Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x    x = 4 x 20
5

x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Discussion:
94 comments Page 8 of 10.

Siddharth said:   1 decade ago
Thanks kamal you are right.

Aisha said:   1 decade ago
Sakshi is doing work with x efficiency.

Tanya is doing work with x+25% of x efficiency.

Sakshi = x work.

Tanya = x+25/100x+125x/100 = 5/4x work.

ATQ,

Sakshi is taking 20 days means x ----> 20 days.

5/4x ----> 20 x 4/5 = 16 days.

Raghu said:   10 years ago
The answer is 15 let me tell you.

Tanya is 25% efficient than Sakshi.

If Sakshi do a work in 24 hours then Tanya will do in 18 hours because 12 is 50% of 24. 6 is 25% of 24.

So Tanya take 6 hours less time than Sakshi, so reduce 6 hours in every day upto 20 days 6 x 20 = 120 i.e 5 days.

20 days - 5 days = 15 days.

Devi prasad said:   10 years ago
Their is mixed view of this question but we got both the answer correctly.

Vamsi said:   1 decade ago
If Tanya is 25% more efficient than Sakshi, then as 25% of 20 is 5. Tanya should complete the work in 15 days not 16 days.

Vijayalakshmi R said:   1 decade ago
S can do a work in 20 days so, s=1/20;

T can do a work 25% more efficient than S.

So, T = 1/20 + (25/100*1/20).

Finally we got T = 1/16.

So 16 is the correct answer.

I am sure about my answer so don't confuse, it may be 25 or other else.

Sanjoy said:   1 decade ago
100T = 125S, 20S = 1, consider x day required for Tania.

4T = 5S, S = 1/20, Tx =1.
4T = 5*1/20 1/16x = 1.

4T = 1/4 x = 16.
T = 1/16.

So Tania required 16days to complete the work.

Jitendra said:   1 decade ago
Why we should consider 125 and 100.

If we consider that Sakshi 100 and Tanya 75 then,

100 : 75 :: 20 : x.

= 100/75 = 20/x.

=> x = 15 days.

Jitendra said:   1 decade ago
Let Sakshi completes the whole work = 100 days.

Then Tanya will complete it = 75 days.

Now, 100 = 20.

1 = 20/100 = 1/5.

75 = (1/5) *75 = 15 days.

So answer should be 15 days.

Priya said:   1 decade ago
Nothing to do all this just simple calculation in question it is given Tanya is 25% more efficient than Sakshi which do in 20 days.

So Tanya will do 125/100*1/20 = 4 days.


Post your comments here:

Your comments will be displayed after verification.