Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 20)
20.
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
15
16
18
25
Answer: Option
Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x    x = 4 x 20
5

x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Discussion:
94 comments Page 3 of 10.

Moses said:   8 years ago
15 is the answer because we are reducing Sakshi's work time by 25% Hence multiply 20 days by 0.75 which will give 15days.

15 days is definitely the answer.

Cheenu said:   9 years ago
Can anybody explain this how x = 16 has come from this equation 5:4::20:x?

Soniya said:   9 years ago
Ratio of work done by Tanya and Sakshi = 125 : 100 = 5 : 4.
Ratio of times taken by Tanya and Sakshi = 4 : 5.
5x = 20days. ( Sakshi can complete the work in 20 days).
x = 4.
So, Tanya can finish the work in 16 days.

Ayush said:   9 years ago
@All.

Refer the post of Kamlesh It's quite easy to understand, Thanks @Kamlesh.

Aashi Mehta said:   9 years ago
If we solve in accordance with the question then the answer will be 15 I don't know why every body has taken it as 16.

Please tell me.

Bulu said:   9 years ago
Shaki = 20 days,

Tanya = 25% more efficient,

So that 25% of 20 = 5,

20 days - 5 days = 15 days.

Santosh said:   9 years ago
Thanks @Kamlesh.

Narayan said:   9 years ago
Let the ans is 15 then,

Efficiency=((20 - 15)/15) * 100 = 33.33%(wrong).

Take ans as 16 then,
Efficiency = ((20 - 16)/16) * 100 = 25%(correct).

Sanjay said:   8 years ago
Tanya 1 day =100 unit (make).
Sakshi 1 day =75 unit.
Sakshi 20 days = 1500 unit make ( so this is total work ).

Then tanya make = 1500 / 100 = 15 days.

15 days 1500 unit.

15 --> Can Be Answer.

Shadab Akhtar said:   9 years ago
Sakshi = 1/20 (given).
Tanya = (125/100) * Sakshi (Tanya is 25% more efficient than Sakshi).
Tanya= (125/100) * 1/20.
= 1/16.

Hence, Tanya does the same piece of work in 16 days.


Post your comments here:

Your comments will be displayed after verification.