Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
Answer: Option
Explanation:
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
![]() |
1 | and Q's 1 hour's work = | 1 | . |
96 | 80 |
(P + Q)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 11 | . |
96 | 80 | 480 |
So, both P and Q will finish the work in | ![]() |
480 | ![]() |
hrs. |
11 |
![]() |
![]() |
480 | x | 1 | ![]() |
= | 60 | days = 5 | 5 | days. |
11 | 8 | 11 | 11 |
Discussion:
57 comments Page 3 of 6.
ARCHANA said:
1 decade ago
I could not understand this question can anyone explain it please.
Nagesh G S said:
1 decade ago
The total amount work done is 480/11, but we can not divide it by 8. Because P works for 8 hours a day and Q works for 10 hours a day.
Instead we have to calculate the amount of work done by P per day + amount of work done by Q per day, The take the reciprocal.
If we do that we get:
P = 1/96*8 = 1/12 units of work per day.
Q = 1/80*10 = 1/8 units of work per day.
Amount of work done By P+Q per day = 1/8 + 1/12 = 5/24.
Therefore to complete the entire work it will take 24/5 days.
That's equal to 4 4/5 days.
Instead we have to calculate the amount of work done by P per day + amount of work done by Q per day, The take the reciprocal.
If we do that we get:
P = 1/96*8 = 1/12 units of work per day.
Q = 1/80*10 = 1/8 units of work per day.
Amount of work done By P+Q per day = 1/8 + 1/12 = 5/24.
Therefore to complete the entire work it will take 24/5 days.
That's equal to 4 4/5 days.
Singham said:
8 years ago
If the equation is multiple with 1/8, then how could be possible that the is 5*5/11?
Tuhinaa said:
9 years ago
The explanation is a bit lengthy. Is there any shortcut to solve it.
Bhagyasri said:
9 years ago
1-hour work of p and q is(1/12*8+1/8*10) = 11/480.
8-hours of work is (11/480)*8 = 11/60.
For example, 1 day work is 1/x days then the total number of days is x.
Similarly, 8 hours of work is 11/60 then the total number of days is 60/11.
8-hours of work is (11/480)*8 = 11/60.
For example, 1 day work is 1/x days then the total number of days is x.
Similarly, 8 hours of work is 11/60 then the total number of days is 60/11.
Hariom pundir said:
8 years ago
25 men take 20 days to finish some work, after every 10 days 5 men leave the work, then in how many days will the work be finished? Explain the answer.
Ash said:
8 years ago
Why 12*8 is taken? 12 days n 8 hrs =96hrs how it comes?
Please explain it.
Please explain it.
Amritha said:
8 years ago
@Ash
For 1 day P works for 8hours, then for 12 days (Since P completes the work in 12days.), the total no of hours is 96 hours(12 * 8).
For 1 day P works for 8hours, then for 12 days (Since P completes the work in 12days.), the total no of hours is 96 hours(12 * 8).
Supriya said:
8 years ago
We should take as 1/12 that means 1/n for every question noo. But in this question why we have taken as 12*8, why can't 1/12*8?
Anyone explain me.
Anyone explain me.
Shridhar said:
1 decade ago
Sagarika your explaination is very nice.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers