Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5 5
11
5 6
11
6 5
11
6 6
11
Answer: Option
Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P's1 hour's work = 1 and Q's 1 hour's work = 1 .
96 80

(P + Q)'s 1 hour's work = 1 + 1 = 11 .
96 80 480

So, both P and Q will finish the work in 480 hrs.
11

Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

Discussion:
58 comments Page 3 of 6.

Ash said:   9 years ago
Why 12*8 is taken? 12 days n 8 hrs =96hrs how it comes?

Please explain it.

Amritha said:   9 years ago
@Ash

For 1 day P works for 8hours, then for 12 days (Since P completes the work in 12days.), the total no of hours is 96 hours(12 * 8).

Akila said:   2 decades ago
11/480 is the part of work completed in 1 hour.

If we reverse it we can get time.

Singham said:   8 years ago
If the equation is multiple with 1/8, then how could be possible that the is 5*5/11?

Supriya said:   8 years ago
We should take as 1/12 that means 1/n for every question noo. But in this question why we have taken as 12*8, why can't 1/12*8?

Anyone explain me.

Nagesh G S said:   1 decade ago
The total amount work done is 480/11, but we can not divide it by 8. Because P works for 8 hours a day and Q works for 10 hours a day.

Instead we have to calculate the amount of work done by P per day + amount of work done by Q per day, The take the reciprocal.

If we do that we get:

P = 1/96*8 = 1/12 units of work per day.

Q = 1/80*10 = 1/8 units of work per day.

Amount of work done By P+Q per day = 1/8 + 1/12 = 5/24.

Therefore to complete the entire work it will take 24/5 days.

That's equal to 4 4/5 days.

SrinivasaReddy said:   2 decades ago
P can do the work in 12days. He do per day 8 hours.

P can do work in total hours is:96.

Same as Q can do work in:80hours.

P's one day work is:1/96.

Q's one day work is:1/80.

P+q one day work is:1/96+1/80=11/480.

P+q work is:480/11.

P+q can done 8 hours per day:480/11*1/8.

Supriya said:   2 decades ago
How can we solve this 480/11 * 1/8..and how came the ans 60/11 ?

Chintan said:   2 decades ago
Neha. . They work to gather 8 hours in 1 day that is shown in que. So ans mult. By 1/8

Rani Maria said:   2 decades ago
Take the LCM of 96,80 then we get 480.
then 1/96 * 480 + 1/80 *480 = 5/480 + 6/480 = 11/480.


Post your comments here:

Your comments will be displayed after verification.