Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5 5
11
5 6
11
6 5
11
6 6
11
Answer: Option
Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P's1 hour's work = 1 and Q's 1 hour's work = 1 .
96 80

(P + Q)'s 1 hour's work = 1 + 1 = 11 .
96 80 480

So, both P and Q will finish the work in 480 hrs.
11

Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

Discussion:
57 comments Page 2 of 6.

Rajan said:   5 years ago
I want to know they work 8 hrs a day together, what it means they individual work for 8-8 hrs or their combined work is 8 hrs a day? Please, anyone, tell me.
(1)

James Bond said:   1 decade ago
P's total work in hours = 12 day*8 hour = 96 hr.
P's 1 hour work = 1/96.

Q's total work in hours = 8 days*10 hours = 80 hr.
Q's 1 hour work = 1/80.

Now Both work only for 8 hours a day.

P's 8 hr work = 8* (1/96) = 1/12 (P's 1 day work).
Q's 8 hr work = 8* (1/80) = 1/10 (Q's 1 day work).

Now if P and Q work together in how many days they can complete the task.

= 1/ (1/p + 1/q).
= 1/ (1/12 + 1/10).
= 1/ (11/60).
= 60/11.

= (5*11+5) /11 in mixed fraction.

Avinash said:   1 decade ago
Why we are taking (12*8) instead of (1/12*8)? As though taken in previous sums.

Deepak Patgar said:   1 decade ago
B works for 10 hrs a day i.e 2 hrs more than A.
In days he works for 16 hrs more than A.
It is equal to 2 days' work of A.

If B works for 8 hrs a days he would take 8+2=10 days to complete the same work.

Work done by A per day = 1/12.
Work done by B per day = 1/10.

Work done by A and B together in 1 day = (1/12+1/10).
= 11/60.

So number of days required will be 60/11.

Nabil said:   1 decade ago
No need to take hours in picture because number of hours are same.

Simple ab/a+b.

Where a=12 & b=10.

Thank you.

Mishi said:   1 decade ago
P 12 days, 8 hours = 96. Q = 8 days, 10 hours, = 80.

P works 12 days in 8 days.

Q = 80/8 = 10 days.

= 1/12+1/10 = 60/11.

Anjali sharma said:   1 decade ago
Very easy question no any doubt.

ARCHANA said:   1 decade ago
I could not understand this question can anyone explain it please.

Nagesh G S said:   1 decade ago
The total amount work done is 480/11, but we can not divide it by 8. Because P works for 8 hours a day and Q works for 10 hours a day.

Instead we have to calculate the amount of work done by P per day + amount of work done by Q per day, The take the reciprocal.

If we do that we get:

P = 1/96*8 = 1/12 units of work per day.

Q = 1/80*10 = 1/8 units of work per day.

Amount of work done By P+Q per day = 1/8 + 1/12 = 5/24.

Therefore to complete the entire work it will take 24/5 days.

That's equal to 4 4/5 days.

Amritha said:   8 years ago
@Ash

For 1 day P works for 8hours, then for 12 days (Since P completes the work in 12days.), the total no of hours is 96 hours(12 * 8).


Post your comments here:

Your comments will be displayed after verification.