Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
Answer: Option
Explanation:
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
![]() |
1 | and Q's 1 hour's work = | 1 | . |
96 | 80 |
(P + Q)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 11 | . |
96 | 80 | 480 |
So, both P and Q will finish the work in | ![]() |
480 | ![]() |
hrs. |
11 |
![]() |
![]() |
480 | x | 1 | ![]() |
= | 60 | days = 5 | 5 | days. |
11 | 8 | 11 | 11 |
Discussion:
57 comments Page 2 of 6.
Saniya said:
9 years ago
Why did 1/8 is taken in ratio but not the above hours?
(1)
Mr. Mp said:
8 years ago
480/11 is the total hours taken to complete.
Now in days we want, and in a day only 8 hours is worked as said in question
so, (480/11) / 8 nothing but (480/11)*1/8.
Still confused look at this I complete the work in 40 hours, the company says I can work only 10 hours per day, so how many days it took. nothing but 40/10 or 40 * (1/10) = 4 days.
Now in days we want, and in a day only 8 hours is worked as said in question
so, (480/11) / 8 nothing but (480/11)*1/8.
Still confused look at this I complete the work in 40 hours, the company says I can work only 10 hours per day, so how many days it took. nothing but 40/10 or 40 * (1/10) = 4 days.
(1)
Rajan said:
5 years ago
I want to know they work 8 hrs a day together, what it means they individual work for 8-8 hrs or their combined work is 8 hrs a day? Please, anyone, tell me.
(1)
Henry said:
10 years ago
What amount of work are they to complete?
Deepak Patgar said:
1 decade ago
@Sumasree.
Suppose if A does a work in 8 days, amount of work done by him in 1 day will be 1/8,
Its the reciprocal.
In the same way if both of them does 11/60 work in 1 day they will require 60/11 days to complete that work.
Suppose if A does a work in 8 days, amount of work done by him in 1 day will be 1/8,
Its the reciprocal.
In the same way if both of them does 11/60 work in 1 day they will require 60/11 days to complete that work.
James Bond said:
1 decade ago
P's total work in hours = 12 day*8 hour = 96 hr.
P's 1 hour work = 1/96.
Q's total work in hours = 8 days*10 hours = 80 hr.
Q's 1 hour work = 1/80.
Now Both work only for 8 hours a day.
P's 8 hr work = 8* (1/96) = 1/12 (P's 1 day work).
Q's 8 hr work = 8* (1/80) = 1/10 (Q's 1 day work).
Now if P and Q work together in how many days they can complete the task.
= 1/ (1/p + 1/q).
= 1/ (1/12 + 1/10).
= 1/ (11/60).
= 60/11.
= (5*11+5) /11 in mixed fraction.
P's 1 hour work = 1/96.
Q's total work in hours = 8 days*10 hours = 80 hr.
Q's 1 hour work = 1/80.
Now Both work only for 8 hours a day.
P's 8 hr work = 8* (1/96) = 1/12 (P's 1 day work).
Q's 8 hr work = 8* (1/80) = 1/10 (Q's 1 day work).
Now if P and Q work together in how many days they can complete the task.
= 1/ (1/p + 1/q).
= 1/ (1/12 + 1/10).
= 1/ (11/60).
= 60/11.
= (5*11+5) /11 in mixed fraction.
Avinash said:
1 decade ago
Why we are taking (12*8) instead of (1/12*8)? As though taken in previous sums.
Nabil said:
1 decade ago
No need to take hours in picture because number of hours are same.
Simple ab/a+b.
Where a=12 & b=10.
Thank you.
Simple ab/a+b.
Where a=12 & b=10.
Thank you.
Mishi said:
1 decade ago
P 12 days, 8 hours = 96. Q = 8 days, 10 hours, = 80.
P works 12 days in 8 days.
Q = 80/8 = 10 days.
= 1/12+1/10 = 60/11.
P works 12 days in 8 days.
Q = 80/8 = 10 days.
= 1/12+1/10 = 60/11.
Anjali sharma said:
1 decade ago
Very easy question no any doubt.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers