Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5 5
11
5 6
11
6 5
11
6 6
11
Answer: Option
Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P's1 hour's work = 1 and Q's 1 hour's work = 1 .
96 80

(P + Q)'s 1 hour's work = 1 + 1 = 11 .
96 80 480

So, both P and Q will finish the work in 480 hrs.
11

Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

Discussion:
57 comments Page 2 of 6.

Saniya said:   9 years ago
Why did 1/8 is taken in ratio but not the above hours?
(1)

Mr. Mp said:   8 years ago
480/11 is the total hours taken to complete.

Now in days we want, and in a day only 8 hours is worked as said in question
so, (480/11) / 8 nothing but (480/11)*1/8.

Still confused look at this I complete the work in 40 hours, the company says I can work only 10 hours per day, so how many days it took. nothing but 40/10 or 40 * (1/10) = 4 days.
(1)

Rajan said:   5 years ago
I want to know they work 8 hrs a day together, what it means they individual work for 8-8 hrs or their combined work is 8 hrs a day? Please, anyone, tell me.
(1)

Henry said:   10 years ago
What amount of work are they to complete?

Deepak Patgar said:   1 decade ago
@Sumasree.

Suppose if A does a work in 8 days, amount of work done by him in 1 day will be 1/8,

Its the reciprocal.
In the same way if both of them does 11/60 work in 1 day they will require 60/11 days to complete that work.

James Bond said:   1 decade ago
P's total work in hours = 12 day*8 hour = 96 hr.
P's 1 hour work = 1/96.

Q's total work in hours = 8 days*10 hours = 80 hr.
Q's 1 hour work = 1/80.

Now Both work only for 8 hours a day.

P's 8 hr work = 8* (1/96) = 1/12 (P's 1 day work).
Q's 8 hr work = 8* (1/80) = 1/10 (Q's 1 day work).

Now if P and Q work together in how many days they can complete the task.

= 1/ (1/p + 1/q).
= 1/ (1/12 + 1/10).
= 1/ (11/60).
= 60/11.

= (5*11+5) /11 in mixed fraction.

Avinash said:   1 decade ago
Why we are taking (12*8) instead of (1/12*8)? As though taken in previous sums.

Nabil said:   1 decade ago
No need to take hours in picture because number of hours are same.

Simple ab/a+b.

Where a=12 & b=10.

Thank you.

Mishi said:   1 decade ago
P 12 days, 8 hours = 96. Q = 8 days, 10 hours, = 80.

P works 12 days in 8 days.

Q = 80/8 = 10 days.

= 1/12+1/10 = 60/11.

Anjali sharma said:   1 decade ago
Very easy question no any doubt.


Post your comments here:

Your comments will be displayed after verification.