Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5 5
11
5 6
11
6 5
11
6 6
11
Answer: Option
Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P's1 hour's work = 1 and Q's 1 hour's work = 1 .
96 80

(P + Q)'s 1 hour's work = 1 + 1 = 11 .
96 80 480

So, both P and Q will finish the work in 480 hrs.
11

Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

Discussion:
57 comments Page 2 of 6.

Jakrik said:   6 years ago
p to complete eating chocolate(12*8)=96hrs (work=chocolate).
q to complete eating chocolate(10*8)=80 hrs.
LCM of 96&80=480.
p->5 chocolates/hr(480/96).
Q->6 chocolates/hr(480/80).

In 1 hour = 5+6 = 11 chocolates.
8 hour =11 * 8 = 88(in one day)
Total chocolates = 480.
Days taken to complete = 480/88 = 60/11 = 5 5/11.
(23)

Jitendra Gupta said:   1 decade ago
We can simply do the following!

Convert both the person's work into days bringing the same hours/day so the Man Days remain unchanged!!

Where P works 8 hour/Day working 12 Days= Man Days 96

Where Q works 8 hours / Day working 10 days= Man days 80


Now 1/10 + 1/12

So 11/60 per day work by both

so 60/11 = 5 5/11

Jaydeep Lalakiya said:   5 years ago
P = 12 days = 8 hours, hence P = 1/12 --> (i)
Q = 8 days = 10 hours.

So Q works 10 hours for 8 days so how many days he will take if he works for 8 hours only?
=8*10/8 = 10 days hence Q = 1/10--> (ii)

So now if both work together 1/12+1/10 = 11/60, (5 * 5/11 would be the answer).
(5)

SrinivasaReddy said:   1 decade ago
P can do the work in 12days. He do per day 8 hours.

P can do work in total hours is:96.

Same as Q can do work in:80hours.

P's one day work is:1/96.

Q's one day work is:1/80.

P+q one day work is:1/96+1/80=11/480.

P+q work is:480/11.

P+q can done 8 hours per day:480/11*1/8.

Dileep said:   1 decade ago
Given p can complete the work in 12 days working 8hrs a day.

i.e p - 12 days - 8 hrs.

lly, q - 8 days - 10 hrs (or) 10 days - 8 hrs.

Thus, p+q - x days - 8 hrs.

Hence p + q = 1/12 + 1/10.

= 22/120.

= 11/60.

Therefore p+q can complete the work in 60/11 days.

Bhagyasri said:   8 years ago
1-hour work of p and q is(1/12*8+1/8*10) = 11/480.
8-hours of work is (11/480)*8 = 11/60.
For example, 1 day work is 1/x days then the total number of days is x.
Similarly, 8 hours of work is 11/60 then the total number of days is 60/11.

Sush said:   1 decade ago
@Deeps

For 1hr-11/480th part of work is done.

So, to complete whole work it'll take 480/11hrs.

Eg:
For 1hr-1/4th f work
For xhr-1(whole) work..? x=4hrs.

Just take it to the l.h.s from r.h.s thats it.

Hope you are clear now...:)

Deepak Patgar said:   1 decade ago
@Sumasree.

Suppose if A does a work in 8 days, amount of work done by him in 1 day will be 1/8,

Its the reciprocal.
In the same way if both of them does 11/60 work in 1 day they will require 60/11 days to complete that work.

Nagu said:   2 decades ago
Hi all

we can write 60/11 = (5*11+5)/11
= (55+11)/11

it is same as 5 5/11 here first first 5 is quocient and senocd 5 is remainder and 11 is deviser

Rajan said:   5 years ago
I want to know they work 8 hrs a day together, what it means they individual work for 8-8 hrs or their combined work is 8 hrs a day? Please, anyone, tell me.
(1)


Post your comments here:

Your comments will be displayed after verification.