Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 14)
14.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5 5
11
5 6
11
6 5
11
6 6
11
Answer: Option
Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P's1 hour's work = 1 and Q's 1 hour's work = 1 .
96 80

(P + Q)'s 1 hour's work = 1 + 1 = 11 .
96 80 480

So, both P and Q will finish the work in 480 hrs.
11

Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

Discussion:
57 comments Page 6 of 6.

Anjali sharma said:   1 decade ago
Very easy question no any doubt.

Suresh said:   2 decades ago
How come 5 5/11 days from 60/11?

Sikha said:   1 decade ago
Why multipled by 1/8 not 8?

Neha said:   1 decade ago
Why multiplied by (1/8)?

Hanmant said:   2 decades ago
How come 11/480?

Deepak said:   2 decades ago
How come 11/480?

Baljeet said:   1 decade ago
Good jitendra.