Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 6)
6.
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
0.50
0.66
0.84
0.95
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
27 comments Page 2 of 3.

Udita Jain said:   1 decade ago
Sigma = 3.
Te = 3+8+6 = 17.
(20-17)/3 = 1.

So probability = 84%.

Chandu said:   2 years ago
Z = (20-17)/√(1²+2²+2²),
Z = (20-17)/3,
Z = 1,
So P(1)= 0.842.

Harsh said:   8 years ago
I am not getting it, please explain in detail.

Mastan said:   6 years ago
@All.

Here standard deviation means "sigma".
(1)

Sumit agrawal said:   1 decade ago
Tell me about this question in detail.

Prakash patel said:   1 decade ago
What is sigma? Please explain briefly.

Sumit Patil said:   7 years ago
Yeah, 0. 66 is right. I agree @Nir.

Ramanathan said:   1 decade ago
What is the 20? Is it from formula?

Pawan said:   6 years ago
Yeah, 0.66 is right the right one.
(1)

Sachin said:   10 years ago
(20-3-8-6)/(1^2+2^2+2^2)^1/2 = 1.