6.
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
Discussion:
27 comments Page 2 of 3.
Kapilkotadiya said:
6 years ago
It is working on the function of Z which is denoted by Z(1)=0.84, therefore the answer is 0.84.
Thanks.
Thanks.
Sumit Patil said:
7 years ago
Yeah, 0. 66 is right. I agree @Nir.
Harsh said:
8 years ago
I am not getting it, please explain in detail.
Dishant said:
8 years ago
Why 1*1?
Yawer abbas said:
1 decade ago
how we calculate project completion time probability through mean time of critical activities and standard deviation eaxmple:
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is.
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is.
Jayesh Chavda said:
9 years ago
Which Z table? @Chigumbura.
Chigumbura said:
9 years ago
Standard deviation = square root of (variance) = square root of (1 * 1 + 2 * 2 + 2 * 2) = square root of (9) = 3.
D = 20.
S = 3 + 8 + 6 = 17.
Probability = (D - S)/standard deviation = 1.
Now, from Z table probability = 0.84.
D = 20.
S = 3 + 8 + 6 = 17.
Probability = (D - S)/standard deviation = 1.
Now, from Z table probability = 0.84.
Sushant Bhalla said:
9 years ago
Check the table @Jerrin.
Jerrin said:
9 years ago
Then how it become 84%?
Sachin said:
10 years ago
(20-3-8-6)/(1^2+2^2+2^2)^1/2 = 1.