Which of the following are the guidelines for the construction of a network diagram?
Each activity is represented by one and only one arrow in the network.
Dangling must be avoided in a network diagram.
Dummy activity consumes no time or resource.
all of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Rkp05 said:   5 years ago
Activity is represented by a unique Arrow per activity, whereas Event in CPM is represented by a Circle.

Vineeshkumar said:   6 years ago
Didn't understand the first option can anyone explain?