Which of the following are the guidelines for the construction of a network diagram?

[A]. Each activity is represented by one and only one arrow in the network.
[B]. Dangling must be avoided in a network diagram.
[C]. Dummy activity consumes no time or resource.
[D]. all of the above

Answer: Option D

Explanation:

No answer description available for this question.