PERT requires
single time estimate
double time estimate
triple time estimate
none of these
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Jeya vishnu said:   1 decade ago
Optimistic time + 4* Most likely time + Pessimistic time / 6.

Sagar chavab said:   4 years ago
Pert require triple time and CPM requires a single time estimate.