Electronics and Communication Engineering - Microprocessors - Discussion

Discussion Forum : Microprocessors - Section 7 (Q.No. 18)
18.
A mP contains 2 MHz crystal. The time taken to complete instructions with 1000 cycles is
2 ms
1 ms
2 nx
1 ns
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Madhura said:   1 decade ago
Fclk = Fcrystal/2.
= 2 MHz/2.
= 1 MHz.

Time taken = 1000/1 MHz = 1 ms.