Current Affairs - Business - Discussion
Discussion Forum : Business - Latest Current Affairs (Q.No. 1255)
1255.
Which company commissioned the 1st unit of 110 MW of the Kishanganga hydroelectric project (HEP) of NHPC in Jammu and Kashmir?
Answer: Option
Explanation:
State-run power equipment maker BHEL commissioned 1st unit of 110 MW of the Kishanganga hydroelectric project (HEP) of NHPC in Jammu and Kashmir. It is Located on the river Kishanganga, a tributary of the Jhelum in Bandipora district, all the three units of the 340 MW project will generate 1,350 million units (MU) of clean electricity annually. The other two units are also in advanced stages of commissioning. In J&K, Bhel has so far commissioned 31 Hydro sets with a cumulative capacity of 1,257 MW.
Discussion:
Be the first person to comment on this question !
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers