4. 

Critical path of the PERT chart is:

[A]. path which takes the longest time to complete the project
[B]. the shortest path
[C]. both of the above
[D]. path which takes the shortest time to complete the project
[E]. None of the above

Answer: Option A

Explanation:

No answer description available for this question.

Najaf Ali said: (Aug 1, 2019)  
A PERT chart is a project management tool that provides a graphical representation of a project's timeline.

A PERT chart allows managers to evaluate the time and resources necessary to manage a project.

WORST time is to be found by This chart.